Musi Project
Musi Project in Telangana was 72% full on 26 November 2026, against a normal of 89% for the week and 96% a year earlier. It is one of 50 reservoirs in CWC's South region.
72%full nowNormal 89%
- Stored of 0.123 BCM live capacity
- 0.089 BCM
- Against normal for the week
- −18%
- Below full reservoir level of 196.60 m
- 1.47 m
- Irrigated area served
- 12k ha
Weekly storage
Every Thursday bulletin since 3 Apr 2025
- Stored
- Normal for the week
- Same week a year earlier
Dam
In the dam register
- Completed1963
- Height above lowest foundation28.04 m
- Length474.58 m
- TypeMasonry Gravity
- RiverMusi, Krishna
- DistrictSuryapet, Telangana
- OwnerTelangana Irrigation and CAD Department
- PurposeIrrigation
- Gross storage0.126 BCM
- Live storage0.123 BCM