Ahmedabad-Dholera Expressway
The first package in the ministry's list opened in Jun 2025, the latest in Oct 2025. 2 packages were still being built on 11 Feb 2026.
- Open, in 2 packages
- 60.5 km
- Being built, in 2 packages
- 48.5 km
- Built so far on unfinished packages, weighted by length
- 100%
- Unfinished packages behind their first target
- 2 of 2
Opened
- 10 Jun 2025Package IV, 38.0 kmAhmedabad - Dholera (Pkg IV) from km. 71.06 to km. 109.019) (Start of DSIR zone - Adhelai Village)
- 28 Oct 2025Package III, 22.5 kmAhmedabad - Dholera (Pkg III) from km. 48.52 to km. 71.06) (Vejallka Village - Start of DSIR zone)
Being built
- First target date
- Date given in February 2026
- Answer date, 11 Feb 2026
2024202520262027
- Package I100% built, 22 kmFirst target Jan 2024. Now expected Jan 2026.
- Package II100% built, 27 kmFirst target Jan 2024. Now expected Feb 2026.
Every package
| Ahmedabad - Dholera (Pkg IV) from km. 71.06 to km. 109.019) (Start of DSIR zone - Adhelai Village) | 38.0 | Open | Jun 2025 | – | – | – |
| Ahmedabad - Dholera (Package II) from km. 22.00 to km. 48.52) [Sindhrej Village - Vejallka Village] | 26.5 | 100% built | – | Jan 2024 | Feb 2026 | 25 months |
| Ahmedabad - Dholera (Pkg III) from km. 48.52 to km. 71.06) (Vejallka Village - Start of DSIR zone) | 22.5 | Open | Oct 2025 | – | – | – |
| Ahmedabad - Dholera (Package I) from km. 0.00 to km. 22.00) [Sardar Patel Ring Road - Sindhrej Village] | 22.0 | 100% built | – | Jan 2024 | Jan 2026 | 25 months |
Sources2
- Rajya Sabha: Project-wise Details of Completed and Commissioned Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page
- Rajya Sabha: Project-wise Details of Commissioning of Ongoing Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page