Ahmedabad-Dholera Expressway

The first package in the ministry's list opened in Jun 2025, the latest in Oct 2025. 2 packages were still being built on 11 Feb 2026.

Open, in 2 packages
60.5 km
Being built, in 2 packages
48.5 km
Built so far on unfinished packages, weighted by length
100%
Unfinished packages behind their first target
2 of 2

Opened

  1. 10 Jun 2025Package IV, 38.0 kmAhmedabad - Dholera (Pkg IV) from km. 71.06 to km. 109.019) (Start of DSIR zone - Adhelai Village)
  2. 28 Oct 2025Package III, 22.5 kmAhmedabad - Dholera (Pkg III) from km. 48.52 to km. 71.06) (Vejallka Village - Start of DSIR zone)

Being built

Ahmedabad-Dholera Expressway packages being built, first target and expected date
  • First target date
  • Date given in February 2026
  • Answer date, 11 Feb 2026
2024202520262027
  1. Package I100% built, 22 kmFirst target Jan 2024. Now expected Jan 2026.
  2. Package II100% built, 27 kmFirst target Jan 2024. Now expected Feb 2026.

Every package

Ahmedabad-Dholera Expressway packages
Ahmedabad - Dholera (Pkg IV) from km. 71.06 to km. 109.019) (Start of DSIR zone - Adhelai Village)38.0OpenJun 2025–––
Ahmedabad - Dholera (Package II) from km. 22.00 to km. 48.52) [Sindhrej Village - Vejallka Village]26.5100% built–Jan 2024Feb 202625 months
Ahmedabad - Dholera (Pkg III) from km. 48.52 to km. 71.06) (Vejallka Village - Start of DSIR zone)22.5OpenOct 2025–––
Ahmedabad - Dholera (Package I) from km. 0.00 to km. 22.00) [Sardar Patel Ring Road - Sindhrej Village]22.0100% built–Jan 2024Jan 202625 months