The ministry's list of expressway works on National Highways, given to Parliament on Feb 2026: every package open, and every one still being built with the date first set for it and the date now expected.

Open, in 36 packages
1,281 km
Being built, in 55 packages
1,624 km
Unfinished packages behind their first target
44 of 55
All expressway the ministry counts, Mar 2026
3,644 km

Corridors

11 corridors, ranked by km open and being built.

Expressway delays

44 of 55 unfinished packages are behind their first target.

Every unfinished expressway package, first target and expected date
  • First target date
  • Date given in February 2026
  • Answer date, 11 Feb 2026
202120222023202420252026202720282029
  1. Ahmedabad-Dholera Expressway
  2. Package I100% built, 22 kmFirst target Jan 2024. Now expected Jan 2026.
  3. Package II100% built, 27 kmFirst target Jan 2024. Now expected Feb 2026.
  4. Bengaluru-Chennai Expressway
  5. Phase I, Package I99% built, 27 kmFirst target May 2024. Now expected Sep 2025.
  6. Phase I, Package II100% built, 27 kmFirst target May 2024. Now expected Sep 2025.
  7. Package P-194% built, 24 kmFirst target May 2024. Now expected Feb 2026.
  8. Phase I, Package III100% built, 18 kmFirst target May 2024. Now expected Sep 2025.
  9. Package P-293% built, 25 kmFirst target Jul 2024. Now expected Apr 2026.
  10. Package P-354% built, 26 kmFirst target Jul 2024. No expected date given.no new date given
  11. Phase II, Package III99% built, 29 kmFirst target Oct 2024. No expected date given.no new date given
  12. Phase II, Package I98% built, 25 kmFirst target Oct 2024. No expected date given.no new date given
  13. Phase II, Package II83% built, 31 kmFirst target Jun 2025. Now expected Jun 2026.
  14. Delhi-Amritsar-Katra Expressway
  15. Amritsar spur 2no progress given, 31 kmNo first target given. No expected date given.no new date given
  16. Package 1100% built, 34 kmFirst target Dec 2023. Now expected Nov 2025.
  17. Package 2100% built, 27 kmFirst target Jan 2024. Now expected Dec 2024.
  18. Package 695% built, 31 kmFirst target May 2024. No expected date given.no new date given
  19. Package 599% built, 38 kmFirst target May 2024. Now expected Feb 2026.
  20. Package 795% built, 37 kmFirst target Jul 2024. Now expected Mar 2026.
  21. Package 1063% built, 40 kmFirst target Jul 2024. No expected date given.no new date given
  22. Package 971% built, 43 kmFirst target Jul 2024. Now expected Jun 2026.
  23. Package 1481% built, 45 kmFirst target Sep 2024. Now expected May 2026.
  24. Package 1589% built, 35 kmFirst target Sep 2024. Now expected Jul 2026.
  25. Package 1692% built, 20 kmFirst target Sep 2024. Now expected Jun 2026.
  26. Amritsar spur 330% built, 28 kmFirst target Oct 2024. Now expected Nov 2026.
  27. Package 1143% built, 43 kmFirst target Nov 2024. No expected date given.no new date given
  28. Package 831% built, 35 kmFirst target Mar 2025. No expected date given.no new date given
  29. Package 1754% built, 27 kmFirst target Jun 2025. Now expected Sep 2026.
  30. Package 1852% built, 15 kmFirst target Nov 2025. Now expected Aug 2026.
  31. Amritsar spur 129% built, 17 kmFirst target Apr 2026. Now expected Mar 2028.
  32. Package 1226% built, 35 kmFirst target Feb 2027. Now expected Feb 2027.
  33. Delhi-Mumbai Expressway
  34. Package V95% built, 25 kmFirst target Oct 2021. Now expected Mar 2026.
  35. Package 3195% built, 19 kmFirst target May 2023. Now expected Feb 2026.
  36. Package 1095% built, 26 kmFirst target May 2023. Now expected Mar 2026.
  37. Package VII97% built, 28 kmFirst target Nov 2023. Now expected Dec 2024.
  38. Package 2896% built, 25 kmFirst target Nov 2023. Now expected Mar 2026.
  39. Package VI99% built, 37 kmFirst target Dec 2023. Now expected Nov 2024.
  40. Package 1590% built, 8 kmFirst target Jan 2024. Now expected Mar 2026.
  41. Package XIII91% built, 27 kmFirst target Feb 2024. Now expected Mar 2026.
  42. Package 2794% built, 26 kmFirst target Feb 2024. Now expected Feb 2026.
  43. Package X36% built, 25 kmFirst target Mar 2024. Now expected Nov 2026.
  44. Package XII98% built, 26 kmFirst target Mar 2024. Now expected Feb 2026.
  45. Package XVA88% built, 7 kmFirst target Mar 2024. Now expected Mar 2026.
  46. Package XI100% built, 26 kmFirst target May 2024. Now expected Feb 2026.
  47. Package 2672% built, 33 kmFirst target Aug 2024. Now expected Mar 2026.
  48. Package XVI93% built, 25 kmFirst target Oct 2024. Now expected Mar 2026.
  49. Package XVII84% built, 10 kmFirst target Jul 2025. Now expected Mar 2026.
  50. Package IX22% built, 27 kmFirst target Oct 2025. Now expected Jun 2026.
  51. Package VIII5% built, 35 kmFirst target Mar 2026. No expected date given.no new date given
  52. Kanpur-Lucknow Expressway
  53. Package II100% built, 45 kmFirst target May 2025. Now expected Feb 2026.
  54. Package 194% built, 18 kmFirst target Jul 2025. Now expected Mar 2026.
  55. Surat-Nashik-Ahmednagar-Solapur Expressway
  56. Package XIV36% built, 36 kmFirst target Oct 2026. Now expected Oct 2026.
  57. Ujjain-Garoth Expressway
  58. Ujjain-Garoth Partial Expressway (NH-752D)99% built, 137 kmFirst target Dec 2023. Now expected Sep 2025.
  59. Varanasi-Ranchi-Kolkata Expressway
  60. Package 127% built, 27 kmFirst target Nov 2026. Now expected May 2027.
  61. Name given as NA
  62. Unnamed package, 17.2 km90% built, 17 kmFirst target May 2024. Now expected Feb 2026.
  63. Unnamed package, 18 km90% built, 18 kmFirst target May 2024. Now expected Feb 2026.
  64. Unnamed package, 31.7 km84% built, 32 kmFirst target Jul 2024. Now expected Jul 2026.

Every package

Every National Highway expressway package, open and being built
Delhi-Mumbai Expressway-MP Portion (NE-4)Delhi-Mumbai Expressway244.5OpenSep 2023–––
Ujjain-Garoth Partial Expressway (NH-752D)Ujjain-Garoth Expressway136.599% built–Dec 2023Sep 202520 months
Four Laning of Ahmedabad-Vadodara Expressway from km.0.000 to km 93.302Ahmedabad-Vadodara Expressway93.3OpenOct 2004–––
4-lane Green Field Expressway Spur from Delhi-Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Ph-I in Rajasthan (HAM) NE-4CDelhi-Mumbai Expressway66.9OpenJun 2025–––
Delhi-Vadodara 8-lane carriageway (km 247.31 to 292.95) Green Filed Alignment under BM, NE-4 (Package-9)Delhi-Mumbai Expressway45.6OpenDec 2023–––
6L Greenfield Kanpur - Lucknow (Expressway) Package II from km. 28.500 to km. 73.744Kanpur-Lucknow Expressway45.2100% built–May 2025Feb 202610 months
Delhi-Amritsar-Katra Expressway Package-14Delhi-Amritsar-Katra Expressway44.681% built–Sep 2024May 202620 months
Delhi Amritsar Katra Package-9Delhi-Amritsar-Katra Expressway43.071% built–Jul 2024Jun 202623 months
Delhi Amritsar Katra Package-11Delhi-Amritsar-Katra Expressway43.043% built–Nov 2024Not given–
Delhi Amritsar Katra Package-10Delhi-Amritsar-Katra Expressway39.563% built–Jul 2024Not given–
Ahmedabad - Dholera (Pkg IV) from km. 71.06 to km. 109.019) (Start of DSIR zone - Adhelai Village)Ahmedabad-Dholera Expressway38.0OpenJun 2025–––
Delhi Amritsar Katra Package-5Delhi-Amritsar-Katra Expressway37.799% built–May 2024Feb 202621 months
Delhi Amritsar Katra Package-7Delhi-Amritsar-Katra Expressway36.995% built–Jul 2024Mar 202621 months
Vadodara Mumbai Expressway Section of NE-4 Package VIDelhi-Mumbai Expressway36.999% built–Dec 2023Nov 202412 months
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-04) (Ch. 78+800 to Ch. 115+700) (HR/Rajasthan Border to Junction with SH-44)Delhi-Mumbai Expressway36.9OpenJun 2022–––
Surat-Nashik-Ahmednagar-Solapur-MH/KTN Border (Greenfield stretch Package-XIV)Surat-Nashik-Ahmednagar-Solapur Expressway36.436% built–Oct 2026Oct 2026On time
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-05) (Ch.115+700 to Ch. 151+840) (Junction atSH-44 to Junction Keshopura road)Delhi-Mumbai Expressway36.1OpenJun 2022–––
Vadodara Mumbai Expressway Section of NE-4 Package VIIIDelhi-Mumbai Expressway35.45% built–Mar 2026Not given–
Delhi Amritsar Katra Package-12Delhi-Amritsar-Katra Expressway35.326% built–Feb 2027Feb 2027On time
Delhi-Amritsar-Katra Expressway Package-15Delhi-Amritsar-Katra Expressway35.289% built–Sep 2024Jul 202622 months
Delhi Amritsar Katra Package-8Delhi-Amritsar-Katra Expressway35.131% built–Mar 2025Not given–
Delhi Amritsar Katra Package-1Delhi-Amritsar-Katra Expressway34.0100% built–Dec 2023Nov 202522 months
Delhi-Vadodara 8-lane carriageway (km 214.26 to 247.31) Green Filed Alignment under BM, NE-4 (Package-8)Delhi-Mumbai Expressway33.1OpenFeb 2023–––
Delhi Vadodara Expressway Section of NE-4 Package-26Delhi-Mumbai Expressway32.872% built–Aug 2024Mar 202619 months
Vadodara Mumbai Expressway Section of NE-4 Package IIDelhi-Mumbai Expressway32.0OpenJan 2024–––
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-03) (Ch. 47+000 to Ch. 78+800) (starting near Khanpur Ghati and ending at HR/RJ Border)Delhi-Mumbai Expressway31.8OpenFeb 2023–––
Delhi-Meerut Expressway, Package-IV - Greenfield Delhi-Meerut Expressway from Dasna to Meerut (Km. 27.740 to Km 59.777) in UP on EPC ModeDelhi-Meerut Expressway31.8OpenMar 2021–––
Name given as NA31.784% built–Jul 2024Jul 202625 months
Delhi-Vadodara 8-lane carriageway starting near Junction with NH-11 to start of ROB near junction with NH-11A (km 183 to 214.26) NE-4 (Package-7)Delhi-Mumbai Expressway31.3OpenJun 2022–––
Delhi-Vadodara 8-lane carriageway starting at Junction with Keshopura Road to Junction with NH-11 (km 151+84 to 183+0) Green Filed Alignment under BM, NE-4 (Package-6)Delhi-Mumbai Expressway31.2OpenMar 2022–––
Vadodara Mumbai Expressway Section of NE-4 Package IIIDelhi-Mumbai Expressway31.0OpenJan 2024–––
Bangalore Chennai Expressway from km 96.000 To 127.000 (Byreddypalli to Bangarupalem) (Phase-II Package-II)Bengaluru-Chennai Expressway31.083% built–Jun 2025Jun 202612 months
Delhi Amritsar Katra Package-6Delhi-Amritsar-Katra Expressway30.995% built–May 2024Not given–
Delhi Amritsar Katra Package-3Delhi-Amritsar-Katra Expressway30.6OpenMay 2024–––
Delhi - Vadodara (Junction with NH- 76 to Junction with NH-12 near village Ummedpura) (Ch 388.42 to Ch. 419), NE-4 (Package-14)Delhi-Mumbai Expressway30.6OpenDec 2024–––
Delhi Amritsar Katra (Amritsar Connectivity) Spur-2Delhi-Amritsar-Katra Expressway30.5Being built––Not given–
Delhi - Vadodara (Junction with SH-37A to Junction with NH- 76 (km. 359.170 to 388.42), NE-4 (Package-13)Delhi-Mumbai Expressway29.3OpenJul 2024–––
Bangalore Chennai Expressway from km.127.000 to Km 156.000 (Bangarupalem to Gudipala section) (Phase-II Package-III)Bengaluru-Chennai Expressway29.099% built–Oct 2024Not given–
Delhi Amritsar Katra Package-4Delhi-Amritsar-Katra Expressway28.9OpenSep 2024–––
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-02) (Ch. 18+500 to Ch. 47+000)(Expressway starting before KMP Expressway and ending at Ch. 47+000 near Khanpur Ghati)Delhi-Mumbai Expressway28.5OpenFeb 2023–––
Delhi - Vadodara (starting near Major Bridge on Mej River - Junction on SH-37A (Ch. 331.030 to 359.170), NE-4 (Package-12)Delhi-Mumbai Expressway28.1OpenMay 2024–––
Delhi Amritsar Katra (Amritsar Connectivity) Spur-3Delhi-Amritsar-Katra Expressway28.130% built–Oct 2024Nov 202625 months
Vadodara Mumbai Expressway Section of NE-4 Package VIIDelhi-Mumbai Expressway27.597% built–Nov 2023Dec 202414 months
Construction 8-lane access controlled Expressway from km. 26.582 to 50.70 of Main Expressway and km.0 to 3 of SPUR (Shirsad to Masvan section of VME), Package-XIII on HAM basis.Delhi-Mumbai Expressway27.291% built–Feb 2024Mar 202626 months
Bangalore-Chennai Expressway Phase I, Package-I of NE-7Bengaluru-Chennai Expressway27.199% built–May 2024Sep 202516 months
Bangalore-Chennai Expressway- Phase I, Package-II of NE-7Bengaluru-Chennai Expressway27.1100% built–May 2024Sep 202516 months
Construction of 6-lane Greenfield Varanasi-Ranchi-Kolkata Expressway (Package-1) from junction with NH-19 & Varanasi Ring Road near Rewasa village to Junction with Chandauli-Chainpur road near Khianti villageVaranasi-Ranchi-Kolkata Expressway27.027% built–Nov 2026May 20276 months
Delhi-Amritsar-Katra Expressway Package-17Delhi-Amritsar-Katra Expressway26.854% built–Jun 2025Sep 202615 months
Delhi Amritsar Katra Package-2Delhi-Amritsar-Katra Expressway26.8100% built–Jan 2024Dec 202411 months
Vadodara Mumbai Expressway Section of NE-4 Package IXDelhi-Mumbai Expressway26.622% built–Oct 2025Jun 20269 months
Ahmedabad - Dholera (Package II) from km. 22.00 to km. 48.52) [Sindhrej Village - Vejallka Village]Ahmedabad-Dholera Expressway26.5100% built–Jan 2024Feb 202625 months
Delhi - Vadodara [End of Interchange on NH-166 near village Mui to Hardeoganj village near Indergarh (Ch 292.95 to 319.40), NE-4 (Package-10]Delhi-Mumbai Expressway26.595% built–May 2023Mar 202634 months
Construction of 8-lane access controlled Expressway from km. 77 to 103.400 (Ganjad to Talasari section of VME), Package-XI on HAM basis.Delhi-Mumbai Expressway26.4100% built–May 2024Feb 202621 months
Delhi Vadodara Expressway Section of NE-4 Package-27Delhi-Mumbai Expressway26.494% built–Feb 2024Feb 202625 months
Construction 8-lane access controlled Expressway from km. 50.700 to 77 (Masvan to Ganjad section of VME), Package-XII on HAM basis.Delhi-Mumbai Expressway26.398% built–Mar 2024Feb 202623 months
4 Lane Bangalore Chennai Expressway (Arakonam to Kancheepuram) section of NE-7 - (P-3)Bengaluru-Chennai Expressway25.554% built–Jul 2024Not given–
Delhi Vadodara Expressway Section of NE-4 Package-28Delhi-Mumbai Expressway25.296% built–Nov 2023Mar 202629 months
Delhi-Vadodara (Start of Bridge near Manoharpur to Rajasthan/MP Border (km. 427.3 to 452.425), NE-4 (Package-16)Delhi-Mumbai Expressway25.1OpenDec 2023–––
Bangalore Chennai Expressway from km.71.000 to Km 96.000 (Bethamangala in the state of Karnataka to Byreddypalli) (Phase-II Package-I)Bengaluru-Chennai Expressway25.098% built–Oct 2024Not given–
Vadodara Mumbai Expressway Section of NE-4 Package XDelhi-Mumbai Expressway24.636% built–Mar 2024Nov 202632 months
Construction of 8-lane access controlled Expressway from km. 45.200 to 69.800 (Amne to Bhoj section - SPUR of VME) basis, Package-XVI on HAM basis.Delhi-Mumbai Expressway24.693% built–Oct 2024Mar 202617 months
Vadodara Mumbai Expressway Section of NE-4 Package VDelhi-Mumbai Expressway24.695% built–Oct 2021Mar 202653 months
Eastern Peripheral Expressway, Package-II - 6-lane of Eastern Peripheral Expressway from km 22.000 to km 46.500 in the States of Haryana and Uttar PradeshEastern Peripheral Expressway24.5OpenMay 2018–––
Eastern Peripheral Expressway, Package-III - 6-lane of Eastern Peripheral Expressway from km 46.500 to km 71.00 in the State of Uttar PradeshEastern Peripheral Expressway24.5OpenMay 2018–––
4 lane Bangalore - Chennai Expressway (Walajahpet - Arakonam) section of NE-7 (P-2)Bengaluru-Chennai Expressway24.593% built–Jul 2024Apr 202622 months
4 lane Bangalore to Chennai Expressway (Gudipala to Walajahpet) section of NE-7 (P-1)Bengaluru-Chennai Expressway24.094% built–May 2024Feb 202621 months
Vadodara Mumbai Expressway Section of NE-4 Package IDelhi-Mumbai Expressway23.7OpenAug 2022–––
Ahmedabad - Dholera (Pkg III) from km. 48.52 to km. 71.06) (Vejallka Village - Start of DSIR zone)Ahmedabad-Dholera Expressway22.5OpenOct 2025–––
Delhi Vadodara Expressway Section of NE-4 Package-29Delhi-Mumbai Expressway22.5OpenMay 2023–––
Eastern Peripheral Expressway, Package-IV - 6-lane of Eastern Peripheral Expressway from Km 71.000 to Km 93.000 in the state of Uttar PradeshEastern Peripheral Expressway22.0OpenMay 2018–––
Eastern Peripheral Expressway, Package-VI - 6-lane of Eastern Peripheral Expressway from Km 114.000 to Km 136.000 in the State of Haryana.Eastern Peripheral Expressway22.0OpenMay 2018–––
Ahmedabad - Dholera (Package I) from km. 0.00 to km. 22.00) [Sardar Patel Ring Road - Sindhrej Village]Ahmedabad-Dholera Expressway22.0100% built–Jan 2024Jan 202625 months
Delhi Vadodara Expressway Section of NE-4 Package-30Delhi-Mumbai Expressway21.5OpenJan 2026–––
Eastern Peripheral Expressway, Package-I - 6-lane of Eastern Peripheral Expressway from km 1.000 to km 22.00 in the States of Haryana and Uttar PradeshEastern Peripheral Expressway21.0OpenMay 2018–––
Eastern Peripheral Expressway, Package-V - 6-lane of Eastern Peripheral Expressway from Km 93.000 to Km 114.000 in the States of Haryana and UP.Eastern Peripheral Expressway21.0OpenMay 2018–––
Delhi-Amritsar-Katra Expressway Package-16Delhi-Amritsar-Katra Expressway20.492% built–Sep 2024Jun 202621 months
Delhi Vadodara Expressway Section of NE-4 Package-31Delhi-Mumbai Expressway19.595% built–May 2023Feb 202633 months
Delhi-Meerut Expressway, Package-II - Delhi-Meerut Expressway from Km. 8.716 to Km. 28.000 (U.P. Border to Dasna) in UP on Hybrid Annuity ModeDelhi-Meerut Expressway19.3OpenMar 2021–––
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-01) (Ch. 0+000 to Ch. 18+461) (Sohna-Gurugram Road (NH-248A) near Alipur Village and ending before KMP Expressway)Delhi-Mumbai Expressway18.5OpenFeb 2023–––
Name given as NA18.090% built–May 2024Feb 202622 months
6L Elevated Kanpur - Lucknow (Expressway) Package-1 from Km. 10+980 to Km. 28+500Kanpur-Lucknow Expressway17.594% built–Jul 2025Mar 20268 months
Bangalore-Chennai Expressway- Phase I, Package-III of NE-7Bengaluru-Chennai Expressway17.5100% built–May 2024Sep 202515 months
Name given as NA17.290% built–May 2024Feb 202622 months
Delhi Amritsar Katra (Amritsar Connectivity) Spur-1Delhi-Amritsar-Katra Expressway16.929% built–Apr 2026Mar 202824 months
Delhi-Amritsar-Katra Expressway Package-18Delhi-Amritsar-Katra Expressway15.352% built–Nov 2025Aug 20269 months
Vadodara Mumbai Expressway Section of NE-4 Package IVDelhi-Mumbai Expressway13.0OpenApr 2024–––
Delhi - Vadodara (starting from Hardeoganj Village near Indergarh to Major Bridge on Maj River (Ch. 319.40 to 331.030), NE-4 (Package-11)Delhi-Mumbai Expressway11.6OpenNov 2023–––
Construction 8-lane access controlled Expressway from Km 69.700 to Km 79.783(Bhoj to Morbe -Spur) Section of VME, Package-XVII on HAM basis.Delhi-Mumbai Expressway10.084% built–Jul 2025Mar 20268 months
Delhi-Meerut Expressway, Package-I - Delhi-Meerut Expressway from Km. 0.00 to Km. 8.716 (Nizamuddin to U.P. Gate) in Delhi on Hybrid Annuity ModeDelhi-Meerut Expressway8.7OpenJun 2018–––
Delhi - Vadodara [Junction with NH-12 to Start of Bridge near Manoharpura] (Ch 419.00 to 427.30), NE-4 (Package-15]Delhi-Mumbai Expressway8.390% built–Jan 2024Mar 202627 months
Construction 8-lane access controlled Expressway from km. 38.200 to 45.200 (Borivali to sange Secton - SPUR of VME), Package-XVA on HAM basis.Delhi-Mumbai Expressway7.088% built–Mar 2024Mar 202624 months

Named expressways, including State ones

Named expressways
Delhi-Mumbai Expressway (operational sections)84582023Delhi - Dausa - Vadodara - Bharuch (partial)NHAI
Samruddhi Mahamarg70162022Mumbai - NagpurMaharashtra State Road Development Corporation
Purvanchal Expressway34162021Lucknow - GhazipurUttar Pradesh Expressways Industrial Development Authority
Agra-Lucknow Expressway30262016Agra - LucknowUttar Pradesh Expressways Industrial Development Authority
Bundelkhand Expressway29642022Chitrakoot - EtawahUttar Pradesh Expressways Industrial Development Authority
Yamuna Expressway16562012Greater Noida - AgraYamuna Expressway Industrial Development Authority
Hyderabad Outer Ring Road15882018Hyderabad ringHyderabad Metropolitan Development Authority
Western Peripheral Expressway (KMP)13662018Kundli - Manesar - PalwalHaryana State Industrial and Infrastructure Development Corporation
Eastern Peripheral Expressway13562018Kundli - Ghaziabad - PalwalNHAI
Bengaluru-Mysuru Expressway119102023Bengaluru - MysuruNHAI
Mumbai-Pune Expressway9462002Mumbai - PuneMaharashtra State Road Development Corporation
Ahmedabad-Vadodara Expressway9342003Ahmedabad - VadodaraNHAI
Delhi-Meerut Expressway82142021Delhi - MeerutNHAI
Chennai Bypass3262010Maduravoyal - TambaramNHAI
Dwarka Expressway2982024Delhi - GurugramNHAI
Eastern Freeway1742013Mumbai (P. D'Mello Road - Ghatkopar)Mumbai Metropolitan Region Development Authority
16 rows3,545

Large Bharatmala sections

Bharatmala project sections
Surat-Chennai ExpresswaySurat-Chennai Expressway1,27150,000Awarded–Gujarat / Maharashtra / Karnataka / Andhra Pradesh / Tamil Nadu
Char Dham All-Weather RoadChar Dham Pariyojana88912,000Being built–Uttarakhand
Delhi-Amritsar-Katra ExpresswayDelhi-Amritsar-Katra Expressway67039,500Being built–Haryana / Punjab / Jammu and Kashmir
Raipur-Visakhapatnam ExpresswayRaipur-Visakhapatnam Economic Corridor46424,000Being built–Chhattisgarh / Odisha / Andhra Pradesh
Delhi-Mumbai Expressway (Dausa - Lalsot - Kota - Ratlam section)Delhi-Mumbai Expressway37418,800Being built–Rajasthan / Madhya Pradesh
Delhi-Mumbai Expressway (Vadodara - Mumbai section)Delhi-Mumbai Expressway35435,100Being built–Gujarat / Maharashtra
Ambala-Kotputli ExpresswayAmbala-Kotputli Economic Corridor31314,000Being built–Haryana / Rajasthan
Bundelkhand ExpresswayBundelkhand Expressway29614,716Open16 Jul 2022Uttar Pradesh
Bengaluru-Chennai ExpresswayBengaluru-Chennai Expressway26216,730Being built–Karnataka / Andhra Pradesh / Tamil Nadu
Delhi-Mumbai Expressway (Sohna - Dausa - Lalsot section)Delhi-Mumbai Expressway24612,150Open12 Feb 2023Haryana / Rajasthan
Delhi-Mumbai Expressway (Vadodara - Bharuch - Surat section)Delhi-Mumbai Expressway1887,600Open9 Dec 2023Gujarat
Eastern Peripheral ExpresswayDelhi NCR Ring13511,000Open27 May 2018Haryana / Uttar Pradesh
Lucknow-Kanpur ExpresswayLucknow-Kanpur Expressway634,700Being built–Uttar Pradesh
Dwarka Expressway (Delhi-Gurugram)Dwarka Expressway299,000Open11 Mar 2024Delhi / Haryana
Zojila TunnelSrinagar-Leh Highway146,800Being built–Jammu and Kashmir / Ladakh
15 rows5,5682,76,096