Expressways
The ministry's list of expressway works on National Highways, given to Parliament on Feb 2026: every package open, and every one still being built with the date first set for it and the date now expected.
- Open, in 36 packages
- 1,281 km
- Being built, in 55 packages
- 1,624 km
- Unfinished packages behind their first target
- 44 of 55
- All expressway the ministry counts, Mar 2026
- 3,644 km
Corridors
11 corridors, ranked by km open and being built.
- Delhi-Mumbai ExpresswayNE-4, 40 packages873 km open, 436 km being built
- Delhi-Amritsar-Katra ExpresswayNE-5, 20 packages60 km open, 580 km being built
- Bengaluru-Chennai ExpresswayNE-7, 9 packages0 km open, 231 km being built
- Ujjain-Garoth Expressway1 package0 km open, 137 km being built
- Eastern Peripheral Expressway6 packages135 km open, 0 km being built
- Ahmedabad-Dholera Expressway4 packages61 km open, 49 km being built
- Ahmedabad-Vadodara ExpresswayNE-1, 1 package93 km open, 0 km being built
- Kanpur-Lucknow Expressway2 packages0 km open, 63 km being built
- Delhi-Meerut Expressway3 packages60 km open, 0 km being built
- Surat-Nashik-Ahmednagar-Solapur Expressway1 package0 km open, 36 km being built
- Varanasi-Ranchi-Kolkata Expressway1 package0 km open, 27 km being built
Expressway delays
44 of 55 unfinished packages are behind their first target.
- First target date
- Date given in February 2026
- Answer date, 11 Feb 2026
202120222023202420252026202720282029
- Ahmedabad-Dholera Expressway
- Package I100% built, 22 kmFirst target Jan 2024. Now expected Jan 2026.
- Package II100% built, 27 kmFirst target Jan 2024. Now expected Feb 2026.
- Bengaluru-Chennai Expressway
- Phase I, Package I99% built, 27 kmFirst target May 2024. Now expected Sep 2025.
- Phase I, Package II100% built, 27 kmFirst target May 2024. Now expected Sep 2025.
- Package P-194% built, 24 kmFirst target May 2024. Now expected Feb 2026.
- Phase I, Package III100% built, 18 kmFirst target May 2024. Now expected Sep 2025.
- Package P-293% built, 25 kmFirst target Jul 2024. Now expected Apr 2026.
- Package P-354% built, 26 kmFirst target Jul 2024. No expected date given.no new date given
- Phase II, Package III99% built, 29 kmFirst target Oct 2024. No expected date given.no new date given
- Phase II, Package I98% built, 25 kmFirst target Oct 2024. No expected date given.no new date given
- Phase II, Package II83% built, 31 kmFirst target Jun 2025. Now expected Jun 2026.
- Delhi-Amritsar-Katra Expressway
- Amritsar spur 2no progress given, 31 kmNo first target given. No expected date given.no new date given
- Package 1100% built, 34 kmFirst target Dec 2023. Now expected Nov 2025.
- Package 2100% built, 27 kmFirst target Jan 2024. Now expected Dec 2024.
- Package 695% built, 31 kmFirst target May 2024. No expected date given.no new date given
- Package 599% built, 38 kmFirst target May 2024. Now expected Feb 2026.
- Package 795% built, 37 kmFirst target Jul 2024. Now expected Mar 2026.
- Package 1063% built, 40 kmFirst target Jul 2024. No expected date given.no new date given
- Package 971% built, 43 kmFirst target Jul 2024. Now expected Jun 2026.
- Package 1481% built, 45 kmFirst target Sep 2024. Now expected May 2026.
- Package 1589% built, 35 kmFirst target Sep 2024. Now expected Jul 2026.
- Package 1692% built, 20 kmFirst target Sep 2024. Now expected Jun 2026.
- Amritsar spur 330% built, 28 kmFirst target Oct 2024. Now expected Nov 2026.
- Package 1143% built, 43 kmFirst target Nov 2024. No expected date given.no new date given
- Package 831% built, 35 kmFirst target Mar 2025. No expected date given.no new date given
- Package 1754% built, 27 kmFirst target Jun 2025. Now expected Sep 2026.
- Package 1852% built, 15 kmFirst target Nov 2025. Now expected Aug 2026.
- Amritsar spur 129% built, 17 kmFirst target Apr 2026. Now expected Mar 2028.
- Package 1226% built, 35 kmFirst target Feb 2027. Now expected Feb 2027.
- Delhi-Mumbai Expressway
- Package V95% built, 25 kmFirst target Oct 2021. Now expected Mar 2026.
- Package 3195% built, 19 kmFirst target May 2023. Now expected Feb 2026.
- Package 1095% built, 26 kmFirst target May 2023. Now expected Mar 2026.
- Package VII97% built, 28 kmFirst target Nov 2023. Now expected Dec 2024.
- Package 2896% built, 25 kmFirst target Nov 2023. Now expected Mar 2026.
- Package VI99% built, 37 kmFirst target Dec 2023. Now expected Nov 2024.
- Package 1590% built, 8 kmFirst target Jan 2024. Now expected Mar 2026.
- Package XIII91% built, 27 kmFirst target Feb 2024. Now expected Mar 2026.
- Package 2794% built, 26 kmFirst target Feb 2024. Now expected Feb 2026.
- Package X36% built, 25 kmFirst target Mar 2024. Now expected Nov 2026.
- Package XII98% built, 26 kmFirst target Mar 2024. Now expected Feb 2026.
- Package XVA88% built, 7 kmFirst target Mar 2024. Now expected Mar 2026.
- Package XI100% built, 26 kmFirst target May 2024. Now expected Feb 2026.
- Package 2672% built, 33 kmFirst target Aug 2024. Now expected Mar 2026.
- Package XVI93% built, 25 kmFirst target Oct 2024. Now expected Mar 2026.
- Package XVII84% built, 10 kmFirst target Jul 2025. Now expected Mar 2026.
- Package IX22% built, 27 kmFirst target Oct 2025. Now expected Jun 2026.
- Package VIII5% built, 35 kmFirst target Mar 2026. No expected date given.no new date given
- Kanpur-Lucknow Expressway
- Package II100% built, 45 kmFirst target May 2025. Now expected Feb 2026.
- Package 194% built, 18 kmFirst target Jul 2025. Now expected Mar 2026.
- Surat-Nashik-Ahmednagar-Solapur Expressway
- Package XIV36% built, 36 kmFirst target Oct 2026. Now expected Oct 2026.
- Ujjain-Garoth Expressway
- Ujjain-Garoth Partial Expressway (NH-752D)99% built, 137 kmFirst target Dec 2023. Now expected Sep 2025.
- Varanasi-Ranchi-Kolkata Expressway
- Package 127% built, 27 kmFirst target Nov 2026. Now expected May 2027.
- Name given as NA
- Unnamed package, 17.2 km90% built, 17 kmFirst target May 2024. Now expected Feb 2026.
- Unnamed package, 18 km90% built, 18 kmFirst target May 2024. Now expected Feb 2026.
- Unnamed package, 31.7 km84% built, 32 kmFirst target Jul 2024. Now expected Jul 2026.
Every package
| Delhi-Mumbai Expressway-MP Portion (NE-4)Delhi-Mumbai Expressway | 244.5 | Open | Sep 2023 | – | – | – |
| Ujjain-Garoth Partial Expressway (NH-752D)Ujjain-Garoth Expressway | 136.5 | 99% built | – | Dec 2023 | Sep 2025 | 20 months |
| Four Laning of Ahmedabad-Vadodara Expressway from km.0.000 to km 93.302Ahmedabad-Vadodara Expressway | 93.3 | Open | Oct 2004 | – | – | – |
| 4-lane Green Field Expressway Spur from Delhi-Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Ph-I in Rajasthan (HAM) NE-4CDelhi-Mumbai Expressway | 66.9 | Open | Jun 2025 | – | – | – |
| Delhi-Vadodara 8-lane carriageway (km 247.31 to 292.95) Green Filed Alignment under BM, NE-4 (Package-9)Delhi-Mumbai Expressway | 45.6 | Open | Dec 2023 | – | – | – |
| 6L Greenfield Kanpur - Lucknow (Expressway) Package II from km. 28.500 to km. 73.744Kanpur-Lucknow Expressway | 45.2 | 100% built | – | May 2025 | Feb 2026 | 10 months |
| Delhi-Amritsar-Katra Expressway Package-14Delhi-Amritsar-Katra Expressway | 44.6 | 81% built | – | Sep 2024 | May 2026 | 20 months |
| Delhi Amritsar Katra Package-9Delhi-Amritsar-Katra Expressway | 43.0 | 71% built | – | Jul 2024 | Jun 2026 | 23 months |
| Delhi Amritsar Katra Package-11Delhi-Amritsar-Katra Expressway | 43.0 | 43% built | – | Nov 2024 | Not given | – |
| Delhi Amritsar Katra Package-10Delhi-Amritsar-Katra Expressway | 39.5 | 63% built | – | Jul 2024 | Not given | – |
| Ahmedabad - Dholera (Pkg IV) from km. 71.06 to km. 109.019) (Start of DSIR zone - Adhelai Village)Ahmedabad-Dholera Expressway | 38.0 | Open | Jun 2025 | – | – | – |
| Delhi Amritsar Katra Package-5Delhi-Amritsar-Katra Expressway | 37.7 | 99% built | – | May 2024 | Feb 2026 | 21 months |
| Delhi Amritsar Katra Package-7Delhi-Amritsar-Katra Expressway | 36.9 | 95% built | – | Jul 2024 | Mar 2026 | 21 months |
| Vadodara Mumbai Expressway Section of NE-4 Package VIDelhi-Mumbai Expressway | 36.9 | 99% built | – | Dec 2023 | Nov 2024 | 12 months |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-04) (Ch. 78+800 to Ch. 115+700) (HR/Rajasthan Border to Junction with SH-44)Delhi-Mumbai Expressway | 36.9 | Open | Jun 2022 | – | – | – |
| Surat-Nashik-Ahmednagar-Solapur-MH/KTN Border (Greenfield stretch Package-XIV)Surat-Nashik-Ahmednagar-Solapur Expressway | 36.4 | 36% built | – | Oct 2026 | Oct 2026 | On time |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-05) (Ch.115+700 to Ch. 151+840) (Junction atSH-44 to Junction Keshopura road)Delhi-Mumbai Expressway | 36.1 | Open | Jun 2022 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package VIIIDelhi-Mumbai Expressway | 35.4 | 5% built | – | Mar 2026 | Not given | – |
| Delhi Amritsar Katra Package-12Delhi-Amritsar-Katra Expressway | 35.3 | 26% built | – | Feb 2027 | Feb 2027 | On time |
| Delhi-Amritsar-Katra Expressway Package-15Delhi-Amritsar-Katra Expressway | 35.2 | 89% built | – | Sep 2024 | Jul 2026 | 22 months |
| Delhi Amritsar Katra Package-8Delhi-Amritsar-Katra Expressway | 35.1 | 31% built | – | Mar 2025 | Not given | – |
| Delhi Amritsar Katra Package-1Delhi-Amritsar-Katra Expressway | 34.0 | 100% built | – | Dec 2023 | Nov 2025 | 22 months |
| Delhi-Vadodara 8-lane carriageway (km 214.26 to 247.31) Green Filed Alignment under BM, NE-4 (Package-8)Delhi-Mumbai Expressway | 33.1 | Open | Feb 2023 | – | – | – |
| Delhi Vadodara Expressway Section of NE-4 Package-26Delhi-Mumbai Expressway | 32.8 | 72% built | – | Aug 2024 | Mar 2026 | 19 months |
| Vadodara Mumbai Expressway Section of NE-4 Package IIDelhi-Mumbai Expressway | 32.0 | Open | Jan 2024 | – | – | – |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-03) (Ch. 47+000 to Ch. 78+800) (starting near Khanpur Ghati and ending at HR/RJ Border)Delhi-Mumbai Expressway | 31.8 | Open | Feb 2023 | – | – | – |
| Delhi-Meerut Expressway, Package-IV - Greenfield Delhi-Meerut Expressway from Dasna to Meerut (Km. 27.740 to Km 59.777) in UP on EPC ModeDelhi-Meerut Expressway | 31.8 | Open | Mar 2021 | – | – | – |
| Name given as NA | 31.7 | 84% built | – | Jul 2024 | Jul 2026 | 25 months |
| Delhi-Vadodara 8-lane carriageway starting near Junction with NH-11 to start of ROB near junction with NH-11A (km 183 to 214.26) NE-4 (Package-7)Delhi-Mumbai Expressway | 31.3 | Open | Jun 2022 | – | – | – |
| Delhi-Vadodara 8-lane carriageway starting at Junction with Keshopura Road to Junction with NH-11 (km 151+84 to 183+0) Green Filed Alignment under BM, NE-4 (Package-6)Delhi-Mumbai Expressway | 31.2 | Open | Mar 2022 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package IIIDelhi-Mumbai Expressway | 31.0 | Open | Jan 2024 | – | – | – |
| Bangalore Chennai Expressway from km 96.000 To 127.000 (Byreddypalli to Bangarupalem) (Phase-II Package-II)Bengaluru-Chennai Expressway | 31.0 | 83% built | – | Jun 2025 | Jun 2026 | 12 months |
| Delhi Amritsar Katra Package-6Delhi-Amritsar-Katra Expressway | 30.9 | 95% built | – | May 2024 | Not given | – |
| Delhi Amritsar Katra Package-3Delhi-Amritsar-Katra Expressway | 30.6 | Open | May 2024 | – | – | – |
| Delhi - Vadodara (Junction with NH- 76 to Junction with NH-12 near village Ummedpura) (Ch 388.42 to Ch. 419), NE-4 (Package-14)Delhi-Mumbai Expressway | 30.6 | Open | Dec 2024 | – | – | – |
| Delhi Amritsar Katra (Amritsar Connectivity) Spur-2Delhi-Amritsar-Katra Expressway | 30.5 | Being built | – | – | Not given | – |
| Delhi - Vadodara (Junction with SH-37A to Junction with NH- 76 (km. 359.170 to 388.42), NE-4 (Package-13)Delhi-Mumbai Expressway | 29.3 | Open | Jul 2024 | – | – | – |
| Bangalore Chennai Expressway from km.127.000 to Km 156.000 (Bangarupalem to Gudipala section) (Phase-II Package-III)Bengaluru-Chennai Expressway | 29.0 | 99% built | – | Oct 2024 | Not given | – |
| Delhi Amritsar Katra Package-4Delhi-Amritsar-Katra Expressway | 28.9 | Open | Sep 2024 | – | – | – |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-02) (Ch. 18+500 to Ch. 47+000)(Expressway starting before KMP Expressway and ending at Ch. 47+000 near Khanpur Ghati)Delhi-Mumbai Expressway | 28.5 | Open | Feb 2023 | – | – | – |
| Delhi - Vadodara (starting near Major Bridge on Mej River - Junction on SH-37A (Ch. 331.030 to 359.170), NE-4 (Package-12)Delhi-Mumbai Expressway | 28.1 | Open | May 2024 | – | – | – |
| Delhi Amritsar Katra (Amritsar Connectivity) Spur-3Delhi-Amritsar-Katra Expressway | 28.1 | 30% built | – | Oct 2024 | Nov 2026 | 25 months |
| Vadodara Mumbai Expressway Section of NE-4 Package VIIDelhi-Mumbai Expressway | 27.5 | 97% built | – | Nov 2023 | Dec 2024 | 14 months |
| Construction 8-lane access controlled Expressway from km. 26.582 to 50.70 of Main Expressway and km.0 to 3 of SPUR (Shirsad to Masvan section of VME), Package-XIII on HAM basis.Delhi-Mumbai Expressway | 27.2 | 91% built | – | Feb 2024 | Mar 2026 | 26 months |
| Bangalore-Chennai Expressway Phase I, Package-I of NE-7Bengaluru-Chennai Expressway | 27.1 | 99% built | – | May 2024 | Sep 2025 | 16 months |
| Bangalore-Chennai Expressway- Phase I, Package-II of NE-7Bengaluru-Chennai Expressway | 27.1 | 100% built | – | May 2024 | Sep 2025 | 16 months |
| Construction of 6-lane Greenfield Varanasi-Ranchi-Kolkata Expressway (Package-1) from junction with NH-19 & Varanasi Ring Road near Rewasa village to Junction with Chandauli-Chainpur road near Khianti villageVaranasi-Ranchi-Kolkata Expressway | 27.0 | 27% built | – | Nov 2026 | May 2027 | 6 months |
| Delhi-Amritsar-Katra Expressway Package-17Delhi-Amritsar-Katra Expressway | 26.8 | 54% built | – | Jun 2025 | Sep 2026 | 15 months |
| Delhi Amritsar Katra Package-2Delhi-Amritsar-Katra Expressway | 26.8 | 100% built | – | Jan 2024 | Dec 2024 | 11 months |
| Vadodara Mumbai Expressway Section of NE-4 Package IXDelhi-Mumbai Expressway | 26.6 | 22% built | – | Oct 2025 | Jun 2026 | 9 months |
| Ahmedabad - Dholera (Package II) from km. 22.00 to km. 48.52) [Sindhrej Village - Vejallka Village]Ahmedabad-Dholera Expressway | 26.5 | 100% built | – | Jan 2024 | Feb 2026 | 25 months |
| Delhi - Vadodara [End of Interchange on NH-166 near village Mui to Hardeoganj village near Indergarh (Ch 292.95 to 319.40), NE-4 (Package-10]Delhi-Mumbai Expressway | 26.5 | 95% built | – | May 2023 | Mar 2026 | 34 months |
| Construction of 8-lane access controlled Expressway from km. 77 to 103.400 (Ganjad to Talasari section of VME), Package-XI on HAM basis.Delhi-Mumbai Expressway | 26.4 | 100% built | – | May 2024 | Feb 2026 | 21 months |
| Delhi Vadodara Expressway Section of NE-4 Package-27Delhi-Mumbai Expressway | 26.4 | 94% built | – | Feb 2024 | Feb 2026 | 25 months |
| Construction 8-lane access controlled Expressway from km. 50.700 to 77 (Masvan to Ganjad section of VME), Package-XII on HAM basis.Delhi-Mumbai Expressway | 26.3 | 98% built | – | Mar 2024 | Feb 2026 | 23 months |
| 4 Lane Bangalore Chennai Expressway (Arakonam to Kancheepuram) section of NE-7 - (P-3)Bengaluru-Chennai Expressway | 25.5 | 54% built | – | Jul 2024 | Not given | – |
| Delhi Vadodara Expressway Section of NE-4 Package-28Delhi-Mumbai Expressway | 25.2 | 96% built | – | Nov 2023 | Mar 2026 | 29 months |
| Delhi-Vadodara (Start of Bridge near Manoharpur to Rajasthan/MP Border (km. 427.3 to 452.425), NE-4 (Package-16)Delhi-Mumbai Expressway | 25.1 | Open | Dec 2023 | – | – | – |
| Bangalore Chennai Expressway from km.71.000 to Km 96.000 (Bethamangala in the state of Karnataka to Byreddypalli) (Phase-II Package-I)Bengaluru-Chennai Expressway | 25.0 | 98% built | – | Oct 2024 | Not given | – |
| Vadodara Mumbai Expressway Section of NE-4 Package XDelhi-Mumbai Expressway | 24.6 | 36% built | – | Mar 2024 | Nov 2026 | 32 months |
| Construction of 8-lane access controlled Expressway from km. 45.200 to 69.800 (Amne to Bhoj section - SPUR of VME) basis, Package-XVI on HAM basis.Delhi-Mumbai Expressway | 24.6 | 93% built | – | Oct 2024 | Mar 2026 | 17 months |
| Vadodara Mumbai Expressway Section of NE-4 Package VDelhi-Mumbai Expressway | 24.6 | 95% built | – | Oct 2021 | Mar 2026 | 53 months |
| Eastern Peripheral Expressway, Package-II - 6-lane of Eastern Peripheral Expressway from km 22.000 to km 46.500 in the States of Haryana and Uttar PradeshEastern Peripheral Expressway | 24.5 | Open | May 2018 | – | – | – |
| Eastern Peripheral Expressway, Package-III - 6-lane of Eastern Peripheral Expressway from km 46.500 to km 71.00 in the State of Uttar PradeshEastern Peripheral Expressway | 24.5 | Open | May 2018 | – | – | – |
| 4 lane Bangalore - Chennai Expressway (Walajahpet - Arakonam) section of NE-7 (P-2)Bengaluru-Chennai Expressway | 24.5 | 93% built | – | Jul 2024 | Apr 2026 | 22 months |
| 4 lane Bangalore to Chennai Expressway (Gudipala to Walajahpet) section of NE-7 (P-1)Bengaluru-Chennai Expressway | 24.0 | 94% built | – | May 2024 | Feb 2026 | 21 months |
| Vadodara Mumbai Expressway Section of NE-4 Package IDelhi-Mumbai Expressway | 23.7 | Open | Aug 2022 | – | – | – |
| Ahmedabad - Dholera (Pkg III) from km. 48.52 to km. 71.06) (Vejallka Village - Start of DSIR zone)Ahmedabad-Dholera Expressway | 22.5 | Open | Oct 2025 | – | – | – |
| Delhi Vadodara Expressway Section of NE-4 Package-29Delhi-Mumbai Expressway | 22.5 | Open | May 2023 | – | – | – |
| Eastern Peripheral Expressway, Package-IV - 6-lane of Eastern Peripheral Expressway from Km 71.000 to Km 93.000 in the state of Uttar PradeshEastern Peripheral Expressway | 22.0 | Open | May 2018 | – | – | – |
| Eastern Peripheral Expressway, Package-VI - 6-lane of Eastern Peripheral Expressway from Km 114.000 to Km 136.000 in the State of Haryana.Eastern Peripheral Expressway | 22.0 | Open | May 2018 | – | – | – |
| Ahmedabad - Dholera (Package I) from km. 0.00 to km. 22.00) [Sardar Patel Ring Road - Sindhrej Village]Ahmedabad-Dholera Expressway | 22.0 | 100% built | – | Jan 2024 | Jan 2026 | 25 months |
| Delhi Vadodara Expressway Section of NE-4 Package-30Delhi-Mumbai Expressway | 21.5 | Open | Jan 2026 | – | – | – |
| Eastern Peripheral Expressway, Package-I - 6-lane of Eastern Peripheral Expressway from km 1.000 to km 22.00 in the States of Haryana and Uttar PradeshEastern Peripheral Expressway | 21.0 | Open | May 2018 | – | – | – |
| Eastern Peripheral Expressway, Package-V - 6-lane of Eastern Peripheral Expressway from Km 93.000 to Km 114.000 in the States of Haryana and UP.Eastern Peripheral Expressway | 21.0 | Open | May 2018 | – | – | – |
| Delhi-Amritsar-Katra Expressway Package-16Delhi-Amritsar-Katra Expressway | 20.4 | 92% built | – | Sep 2024 | Jun 2026 | 21 months |
| Delhi Vadodara Expressway Section of NE-4 Package-31Delhi-Mumbai Expressway | 19.5 | 95% built | – | May 2023 | Feb 2026 | 33 months |
| Delhi-Meerut Expressway, Package-II - Delhi-Meerut Expressway from Km. 8.716 to Km. 28.000 (U.P. Border to Dasna) in UP on Hybrid Annuity ModeDelhi-Meerut Expressway | 19.3 | Open | Mar 2021 | – | – | – |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-01) (Ch. 0+000 to Ch. 18+461) (Sohna-Gurugram Road (NH-248A) near Alipur Village and ending before KMP Expressway)Delhi-Mumbai Expressway | 18.5 | Open | Feb 2023 | – | – | – |
| Name given as NA | 18.0 | 90% built | – | May 2024 | Feb 2026 | 22 months |
| 6L Elevated Kanpur - Lucknow (Expressway) Package-1 from Km. 10+980 to Km. 28+500Kanpur-Lucknow Expressway | 17.5 | 94% built | – | Jul 2025 | Mar 2026 | 8 months |
| Bangalore-Chennai Expressway- Phase I, Package-III of NE-7Bengaluru-Chennai Expressway | 17.5 | 100% built | – | May 2024 | Sep 2025 | 15 months |
| Name given as NA | 17.2 | 90% built | – | May 2024 | Feb 2026 | 22 months |
| Delhi Amritsar Katra (Amritsar Connectivity) Spur-1Delhi-Amritsar-Katra Expressway | 16.9 | 29% built | – | Apr 2026 | Mar 2028 | 24 months |
| Delhi-Amritsar-Katra Expressway Package-18Delhi-Amritsar-Katra Expressway | 15.3 | 52% built | – | Nov 2025 | Aug 2026 | 9 months |
| Vadodara Mumbai Expressway Section of NE-4 Package IVDelhi-Mumbai Expressway | 13.0 | Open | Apr 2024 | – | – | – |
| Delhi - Vadodara (starting from Hardeoganj Village near Indergarh to Major Bridge on Maj River (Ch. 319.40 to 331.030), NE-4 (Package-11)Delhi-Mumbai Expressway | 11.6 | Open | Nov 2023 | – | – | – |
| Construction 8-lane access controlled Expressway from Km 69.700 to Km 79.783(Bhoj to Morbe -Spur) Section of VME, Package-XVII on HAM basis.Delhi-Mumbai Expressway | 10.0 | 84% built | – | Jul 2025 | Mar 2026 | 8 months |
| Delhi-Meerut Expressway, Package-I - Delhi-Meerut Expressway from Km. 0.00 to Km. 8.716 (Nizamuddin to U.P. Gate) in Delhi on Hybrid Annuity ModeDelhi-Meerut Expressway | 8.7 | Open | Jun 2018 | – | – | – |
| Delhi - Vadodara [Junction with NH-12 to Start of Bridge near Manoharpura] (Ch 419.00 to 427.30), NE-4 (Package-15]Delhi-Mumbai Expressway | 8.3 | 90% built | – | Jan 2024 | Mar 2026 | 27 months |
| Construction 8-lane access controlled Expressway from km. 38.200 to 45.200 (Borivali to sange Secton - SPUR of VME), Package-XVA on HAM basis.Delhi-Mumbai Expressway | 7.0 | 88% built | – | Mar 2024 | Mar 2026 | 24 months |
Named expressways, including State ones
| Delhi-Mumbai Expressway (operational sections) | 845 | 8 | 2023 | Delhi - Dausa - Vadodara - Bharuch (partial) | NHAI |
| Samruddhi Mahamarg | 701 | 6 | 2022 | Mumbai - Nagpur | Maharashtra State Road Development Corporation |
| Purvanchal Expressway | 341 | 6 | 2021 | Lucknow - Ghazipur | Uttar Pradesh Expressways Industrial Development Authority |
| Agra-Lucknow Expressway | 302 | 6 | 2016 | Agra - Lucknow | Uttar Pradesh Expressways Industrial Development Authority |
| Bundelkhand Expressway | 296 | 4 | 2022 | Chitrakoot - Etawah | Uttar Pradesh Expressways Industrial Development Authority |
| Yamuna Expressway | 165 | 6 | 2012 | Greater Noida - Agra | Yamuna Expressway Industrial Development Authority |
| Hyderabad Outer Ring Road | 158 | 8 | 2018 | Hyderabad ring | Hyderabad Metropolitan Development Authority |
| Western Peripheral Expressway (KMP) | 136 | 6 | 2018 | Kundli - Manesar - Palwal | Haryana State Industrial and Infrastructure Development Corporation |
| Eastern Peripheral Expressway | 135 | 6 | 2018 | Kundli - Ghaziabad - Palwal | NHAI |
| Bengaluru-Mysuru Expressway | 119 | 10 | 2023 | Bengaluru - Mysuru | NHAI |
| Mumbai-Pune Expressway | 94 | 6 | 2002 | Mumbai - Pune | Maharashtra State Road Development Corporation |
| Ahmedabad-Vadodara Expressway | 93 | 4 | 2003 | Ahmedabad - Vadodara | NHAI |
| Delhi-Meerut Expressway | 82 | 14 | 2021 | Delhi - Meerut | NHAI |
| Chennai Bypass | 32 | 6 | 2010 | Maduravoyal - Tambaram | NHAI |
| Dwarka Expressway | 29 | 8 | 2024 | Delhi - Gurugram | NHAI |
| Eastern Freeway | 17 | 4 | 2013 | Mumbai (P. D'Mello Road - Ghatkopar) | Mumbai Metropolitan Region Development Authority |
| 16 rows | 3,545 |
Large Bharatmala sections
| Surat-Chennai ExpresswaySurat-Chennai Expressway | 1,271 | 50,000 | Awarded | – | Gujarat / Maharashtra / Karnataka / Andhra Pradesh / Tamil Nadu |
| Char Dham All-Weather RoadChar Dham Pariyojana | 889 | 12,000 | Being built | – | Uttarakhand |
| Delhi-Amritsar-Katra ExpresswayDelhi-Amritsar-Katra Expressway | 670 | 39,500 | Being built | – | Haryana / Punjab / Jammu and Kashmir |
| Raipur-Visakhapatnam ExpresswayRaipur-Visakhapatnam Economic Corridor | 464 | 24,000 | Being built | – | Chhattisgarh / Odisha / Andhra Pradesh |
| Delhi-Mumbai Expressway (Dausa - Lalsot - Kota - Ratlam section)Delhi-Mumbai Expressway | 374 | 18,800 | Being built | – | Rajasthan / Madhya Pradesh |
| Delhi-Mumbai Expressway (Vadodara - Mumbai section)Delhi-Mumbai Expressway | 354 | 35,100 | Being built | – | Gujarat / Maharashtra |
| Ambala-Kotputli ExpresswayAmbala-Kotputli Economic Corridor | 313 | 14,000 | Being built | – | Haryana / Rajasthan |
| Bundelkhand ExpresswayBundelkhand Expressway | 296 | 14,716 | Open | 16 Jul 2022 | Uttar Pradesh |
| Bengaluru-Chennai ExpresswayBengaluru-Chennai Expressway | 262 | 16,730 | Being built | – | Karnataka / Andhra Pradesh / Tamil Nadu |
| Delhi-Mumbai Expressway (Sohna - Dausa - Lalsot section)Delhi-Mumbai Expressway | 246 | 12,150 | Open | 12 Feb 2023 | Haryana / Rajasthan |
| Delhi-Mumbai Expressway (Vadodara - Bharuch - Surat section)Delhi-Mumbai Expressway | 188 | 7,600 | Open | 9 Dec 2023 | Gujarat |
| Eastern Peripheral ExpresswayDelhi NCR Ring | 135 | 11,000 | Open | 27 May 2018 | Haryana / Uttar Pradesh |
| Lucknow-Kanpur ExpresswayLucknow-Kanpur Expressway | 63 | 4,700 | Being built | – | Uttar Pradesh |
| Dwarka Expressway (Delhi-Gurugram)Dwarka Expressway | 29 | 9,000 | Open | 11 Mar 2024 | Delhi / Haryana |
| Zojila TunnelSrinagar-Leh Highway | 14 | 6,800 | Being built | – | Jammu and Kashmir / Ladakh |
| 15 rows | 5,568 | 2,76,096 |
Sources5
- Rajya Sabha: Project-wise Details of Completed and Commissioned Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page
- Rajya Sabha: Project-wise Details of Commissioning of Ongoing Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page
- MoRTH: Annual Report 2025-26 (expressways and access-controlled corridors)morth.gov.inPDF document
- NHAI: Project Implementation Unit dashboardnhai.gov.inPublisher page
- PIB: Bharatmala Pariyojana progress (Phase-I, MoRTH)pib.gov.inPublisher page