Bengaluru-Chennai Expressway

NE-7. No package had opened when the ministry answered. 9 packages were still being built on 11 Feb 2026.

Being built, in 9 packages
230.7 km
Built so far on unfinished packages, weighted by length
91%
Unfinished packages behind their first target
6 of 9

Being built

Bengaluru-Chennai Expressway packages being built, first target and expected date
  • First target date
  • Date given in February 2026
  • Answer date, 11 Feb 2026
2024202520262027
  1. Phase I, Package I99% built, 27 kmFirst target May 2024. Now expected Sep 2025.
  2. Phase I, Package II100% built, 27 kmFirst target May 2024. Now expected Sep 2025.
  3. Package P-194% built, 24 kmFirst target May 2024. Now expected Feb 2026.
  4. Phase I, Package III100% built, 18 kmFirst target May 2024. Now expected Sep 2025.
  5. Package P-293% built, 25 kmFirst target Jul 2024. Now expected Apr 2026.
  6. Package P-354% built, 26 kmFirst target Jul 2024. No expected date given.no new date given
  7. Phase II, Package III99% built, 29 kmFirst target Oct 2024. No expected date given.no new date given
  8. Phase II, Package I98% built, 25 kmFirst target Oct 2024. No expected date given.no new date given
  9. Phase II, Package II83% built, 31 kmFirst target Jun 2025. Now expected Jun 2026.

Every package

Bengaluru-Chennai Expressway packages
Bangalore Chennai Expressway from km 96.000 To 127.000 (Byreddypalli to Bangarupalem) (Phase-II Package-II)31.083% built–Jun 2025Jun 202612 months
Bangalore Chennai Expressway from km.127.000 to Km 156.000 (Bangarupalem to Gudipala section) (Phase-II Package-III)29.099% built–Oct 2024Not given–
Bangalore-Chennai Expressway Phase I, Package-I of NE-727.199% built–May 2024Sep 202516 months
Bangalore-Chennai Expressway- Phase I, Package-II of NE-727.1100% built–May 2024Sep 202516 months
4 Lane Bangalore Chennai Expressway (Arakonam to Kancheepuram) section of NE-7 - (P-3)25.554% built–Jul 2024Not given–
Bangalore Chennai Expressway from km.71.000 to Km 96.000 (Bethamangala in the state of Karnataka to Byreddypalli) (Phase-II Package-I)25.098% built–Oct 2024Not given–
4 lane Bangalore - Chennai Expressway (Walajahpet - Arakonam) section of NE-7 (P-2)24.593% built–Jul 2024Apr 202622 months
4 lane Bangalore to Chennai Expressway (Gudipala to Walajahpet) section of NE-7 (P-1)24.094% built–May 2024Feb 202621 months
Bangalore-Chennai Expressway- Phase I, Package-III of NE-717.5100% built–May 2024Sep 202515 months