Bengaluru-Chennai Expressway
NE-7. No package had opened when the ministry answered. 9 packages were still being built on 11 Feb 2026.
- Being built, in 9 packages
- 230.7 km
- Built so far on unfinished packages, weighted by length
- 91%
- Unfinished packages behind their first target
- 6 of 9
Being built
- First target date
- Date given in February 2026
- Answer date, 11 Feb 2026
2024202520262027
- Phase I, Package I99% built, 27 kmFirst target May 2024. Now expected Sep 2025.
- Phase I, Package II100% built, 27 kmFirst target May 2024. Now expected Sep 2025.
- Package P-194% built, 24 kmFirst target May 2024. Now expected Feb 2026.
- Phase I, Package III100% built, 18 kmFirst target May 2024. Now expected Sep 2025.
- Package P-293% built, 25 kmFirst target Jul 2024. Now expected Apr 2026.
- Package P-354% built, 26 kmFirst target Jul 2024. No expected date given.no new date given
- Phase II, Package III99% built, 29 kmFirst target Oct 2024. No expected date given.no new date given
- Phase II, Package I98% built, 25 kmFirst target Oct 2024. No expected date given.no new date given
- Phase II, Package II83% built, 31 kmFirst target Jun 2025. Now expected Jun 2026.
Every package
| Bangalore Chennai Expressway from km 96.000 To 127.000 (Byreddypalli to Bangarupalem) (Phase-II Package-II) | 31.0 | 83% built | – | Jun 2025 | Jun 2026 | 12 months |
| Bangalore Chennai Expressway from km.127.000 to Km 156.000 (Bangarupalem to Gudipala section) (Phase-II Package-III) | 29.0 | 99% built | – | Oct 2024 | Not given | – |
| Bangalore-Chennai Expressway Phase I, Package-I of NE-7 | 27.1 | 99% built | – | May 2024 | Sep 2025 | 16 months |
| Bangalore-Chennai Expressway- Phase I, Package-II of NE-7 | 27.1 | 100% built | – | May 2024 | Sep 2025 | 16 months |
| 4 Lane Bangalore Chennai Expressway (Arakonam to Kancheepuram) section of NE-7 - (P-3) | 25.5 | 54% built | – | Jul 2024 | Not given | – |
| Bangalore Chennai Expressway from km.71.000 to Km 96.000 (Bethamangala in the state of Karnataka to Byreddypalli) (Phase-II Package-I) | 25.0 | 98% built | – | Oct 2024 | Not given | – |
| 4 lane Bangalore - Chennai Expressway (Walajahpet - Arakonam) section of NE-7 (P-2) | 24.5 | 93% built | – | Jul 2024 | Apr 2026 | 22 months |
| 4 lane Bangalore to Chennai Expressway (Gudipala to Walajahpet) section of NE-7 (P-1) | 24.0 | 94% built | – | May 2024 | Feb 2026 | 21 months |
| Bangalore-Chennai Expressway- Phase I, Package-III of NE-7 | 17.5 | 100% built | – | May 2024 | Sep 2025 | 15 months |
Sources2
- Rajya Sabha: Project-wise Details of Completed and Commissioned Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page
- Rajya Sabha: Project-wise Details of Commissioning of Ongoing Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page