Delhi-Mumbai Expressway

NE-4. The first package in the ministry's list opened in Mar 2022, the latest in Jan 2026. 18 packages were still being built on 11 Feb 2026.

Open, in 22 packages
872.8 km
Being built, in 18 packages
435.7 km
Built so far on unfinished packages, weighted by length
78%
Unfinished packages behind their first target
17 of 18

Opened

  1. 10 Mar 2022Package 6, 31.2 kmDelhi-Vadodara 8-lane carriageway starting at Junction with Keshopura Road to Junction with NH-11 (km 151+84 to 183+0) Green Filed Alignment under BM, NE-4 (Package-6)
  2. 26 Jun 2022Package 04, 36.9 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-04) (Ch. 78+800 to Ch. 115+700) (HR/Rajasthan Border to Junction with SH-44)
  3. 28 Jun 2022Package 05, 36.1 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-05) (Ch.115+700 to Ch. 151+840) (Junction atSH-44 to Junction Keshopura road)
  4. 30 Jun 2022Package 7, 31.3 kmDelhi-Vadodara 8-lane carriageway starting near Junction with NH-11 to start of ROB near junction with NH-11A (km 183 to 214.26) NE-4 (Package-7)
  5. 3 Aug 2022Package I, 23.7 kmVadodara Mumbai Expressway Section of NE-4 Package I
  6. 6 Feb 2023Package 8, 33.1 kmDelhi-Vadodara 8-lane carriageway (km 214.26 to 247.31) Green Filed Alignment under BM, NE-4 (Package-8)
  7. 10 Feb 2023Package 01, 18.5 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-01) (Ch. 0+000 to Ch. 18+461) (Sohna-Gurugram Road (NH-248A) near Alipur Village and ending before KMP Expressway)
  8. 10 Feb 2023Package 02, 28.5 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-02) (Ch. 18+500 to Ch. 47+000)(Expressway starting before KMP Expressway and ending at Ch. 47+000 near Khanpur Ghati)
  9. 10 Feb 2023Package 03, 31.8 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-03) (Ch. 47+000 to Ch. 78+800) (starting near Khanpur Ghati and ending at HR/RJ Border)
  10. 16 May 2023Package 29, 22.5 kmDelhi Vadodara Expressway Section of NE-4 Package-29
  11. 20 Sep 2023Delhi-Mumbai Expressway-MP Portion (NE-4), 244.5 kmDelhi-Mumbai Expressway-MP Portion (NE-4)
  12. 30 Nov 2023Package 11, 11.6 kmDelhi - Vadodara (starting from Hardeoganj Village near Indergarh to Major Bridge on Maj River (Ch. 319.40 to 331.030), NE-4 (Package-11)
  13. 30 Dec 2023Package 16, 25.1 kmDelhi-Vadodara (Start of Bridge near Manoharpur to Rajasthan/MP Border (km. 427.3 to 452.425), NE-4 (Package-16)
  14. 31 Dec 2023Package 9, 45.6 kmDelhi-Vadodara 8-lane carriageway (km 247.31 to 292.95) Green Filed Alignment under BM, NE-4 (Package-9)
  15. 9 Jan 2024Package II, 32.0 kmVadodara Mumbai Expressway Section of NE-4 Package II
  16. 10 Jan 2024Package III, 31.0 kmVadodara Mumbai Expressway Section of NE-4 Package III
  17. 2 Apr 2024Package IV, 13.0 kmVadodara Mumbai Expressway Section of NE-4 Package IV
  18. 21 May 2024Package 12, 28.1 kmDelhi - Vadodara (starting near Major Bridge on Mej River - Junction on SH-37A (Ch. 331.030 to 359.170), NE-4 (Package-12)
  19. 28 Jul 2024Package 13, 29.3 kmDelhi - Vadodara (Junction with SH-37A to Junction with NH- 76 (km. 359.170 to 388.42), NE-4 (Package-13)
  20. 31 Dec 2024Package 14, 30.6 kmDelhi - Vadodara (Junction with NH- 76 to Junction with NH-12 near village Ummedpura) (Ch 388.42 to Ch. 419), NE-4 (Package-14)
  21. 1 Jun 20254-lane Green Field Expressway Spur from Delhi-…, 66.9 km4-lane Green Field Expressway Spur from Delhi-Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Ph-I in Rajasthan (HAM) NE-4C
  22. 9 Jan 2026Package 30, 21.5 kmDelhi Vadodara Expressway Section of NE-4 Package-30

Being built

Delhi-Mumbai Expressway packages being built, first target and expected date
  • First target date
  • Date given in February 2026
  • Answer date, 11 Feb 2026
2021202220232024202520262027
  1. Package V95% built, 25 kmFirst target Oct 2021. Now expected Mar 2026.
  2. Package 3195% built, 19 kmFirst target May 2023. Now expected Feb 2026.
  3. Package 1095% built, 26 kmFirst target May 2023. Now expected Mar 2026.
  4. Package VII97% built, 28 kmFirst target Nov 2023. Now expected Dec 2024.
  5. Package 2896% built, 25 kmFirst target Nov 2023. Now expected Mar 2026.
  6. Package VI99% built, 37 kmFirst target Dec 2023. Now expected Nov 2024.
  7. Package 1590% built, 8 kmFirst target Jan 2024. Now expected Mar 2026.
  8. Package XIII91% built, 27 kmFirst target Feb 2024. Now expected Mar 2026.
  9. Package 2794% built, 26 kmFirst target Feb 2024. Now expected Feb 2026.
  10. Package X36% built, 25 kmFirst target Mar 2024. Now expected Nov 2026.
  11. Package XII98% built, 26 kmFirst target Mar 2024. Now expected Feb 2026.
  12. Package XVA88% built, 7 kmFirst target Mar 2024. Now expected Mar 2026.
  13. Package XI100% built, 26 kmFirst target May 2024. Now expected Feb 2026.
  14. Package 2672% built, 33 kmFirst target Aug 2024. Now expected Mar 2026.
  15. Package XVI93% built, 25 kmFirst target Oct 2024. Now expected Mar 2026.
  16. Package XVII84% built, 10 kmFirst target Jul 2025. Now expected Mar 2026.
  17. Package IX22% built, 27 kmFirst target Oct 2025. Now expected Jun 2026.
  18. Package VIII5% built, 35 kmFirst target Mar 2026. No expected date given.no new date given

Every package

Delhi-Mumbai Expressway packages
Delhi-Mumbai Expressway-MP Portion (NE-4)244.5OpenSep 2023–––
4-lane Green Field Expressway Spur from Delhi-Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Ph-I in Rajasthan (HAM) NE-4C66.9OpenJun 2025–––
Delhi-Vadodara 8-lane carriageway (km 247.31 to 292.95) Green Filed Alignment under BM, NE-4 (Package-9)45.6OpenDec 2023–––
Vadodara Mumbai Expressway Section of NE-4 Package VI36.999% built–Dec 2023Nov 202412 months
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-04) (Ch. 78+800 to Ch. 115+700) (HR/Rajasthan Border to Junction with SH-44)36.9OpenJun 2022–––
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-05) (Ch.115+700 to Ch. 151+840) (Junction atSH-44 to Junction Keshopura road)36.1OpenJun 2022–––
Vadodara Mumbai Expressway Section of NE-4 Package VIII35.45% built–Mar 2026Not given–
Delhi-Vadodara 8-lane carriageway (km 214.26 to 247.31) Green Filed Alignment under BM, NE-4 (Package-8)33.1OpenFeb 2023–––
Delhi Vadodara Expressway Section of NE-4 Package-2632.872% built–Aug 2024Mar 202619 months
Vadodara Mumbai Expressway Section of NE-4 Package II32.0OpenJan 2024–––
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-03) (Ch. 47+000 to Ch. 78+800) (starting near Khanpur Ghati and ending at HR/RJ Border)31.8OpenFeb 2023–––
Delhi-Vadodara 8-lane carriageway starting near Junction with NH-11 to start of ROB near junction with NH-11A (km 183 to 214.26) NE-4 (Package-7)31.3OpenJun 2022–––
Delhi-Vadodara 8-lane carriageway starting at Junction with Keshopura Road to Junction with NH-11 (km 151+84 to 183+0) Green Filed Alignment under BM, NE-4 (Package-6)31.2OpenMar 2022–––
Vadodara Mumbai Expressway Section of NE-4 Package III31.0OpenJan 2024–––
Delhi - Vadodara (Junction with NH- 76 to Junction with NH-12 near village Ummedpura) (Ch 388.42 to Ch. 419), NE-4 (Package-14)30.6OpenDec 2024–––
Delhi - Vadodara (Junction with SH-37A to Junction with NH- 76 (km. 359.170 to 388.42), NE-4 (Package-13)29.3OpenJul 2024–––
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-02) (Ch. 18+500 to Ch. 47+000)(Expressway starting before KMP Expressway and ending at Ch. 47+000 near Khanpur Ghati)28.5OpenFeb 2023–––
Delhi - Vadodara (starting near Major Bridge on Mej River - Junction on SH-37A (Ch. 331.030 to 359.170), NE-4 (Package-12)28.1OpenMay 2024–––
Vadodara Mumbai Expressway Section of NE-4 Package VII27.597% built–Nov 2023Dec 202414 months
Construction 8-lane access controlled Expressway from km. 26.582 to 50.70 of Main Expressway and km.0 to 3 of SPUR (Shirsad to Masvan section of VME), Package-XIII on HAM basis.27.291% built–Feb 2024Mar 202626 months
Vadodara Mumbai Expressway Section of NE-4 Package IX26.622% built–Oct 2025Jun 20269 months
Delhi - Vadodara [End of Interchange on NH-166 near village Mui to Hardeoganj village near Indergarh (Ch 292.95 to 319.40), NE-4 (Package-10]26.595% built–May 2023Mar 202634 months
Construction of 8-lane access controlled Expressway from km. 77 to 103.400 (Ganjad to Talasari section of VME), Package-XI on HAM basis.26.4100% built–May 2024Feb 202621 months
Delhi Vadodara Expressway Section of NE-4 Package-2726.494% built–Feb 2024Feb 202625 months
Construction 8-lane access controlled Expressway from km. 50.700 to 77 (Masvan to Ganjad section of VME), Package-XII on HAM basis.26.398% built–Mar 2024Feb 202623 months
Delhi Vadodara Expressway Section of NE-4 Package-2825.296% built–Nov 2023Mar 202629 months
Delhi-Vadodara (Start of Bridge near Manoharpur to Rajasthan/MP Border (km. 427.3 to 452.425), NE-4 (Package-16)25.1OpenDec 2023–––
Vadodara Mumbai Expressway Section of NE-4 Package X24.636% built–Mar 2024Nov 202632 months
Construction of 8-lane access controlled Expressway from km. 45.200 to 69.800 (Amne to Bhoj section - SPUR of VME) basis, Package-XVI on HAM basis.24.693% built–Oct 2024Mar 202617 months
Vadodara Mumbai Expressway Section of NE-4 Package V24.695% built–Oct 2021Mar 202653 months
Vadodara Mumbai Expressway Section of NE-4 Package I23.7OpenAug 2022–––
Delhi Vadodara Expressway Section of NE-4 Package-2922.5OpenMay 2023–––
Delhi Vadodara Expressway Section of NE-4 Package-3021.5OpenJan 2026–––
Delhi Vadodara Expressway Section of NE-4 Package-3119.595% built–May 2023Feb 202633 months
Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-01) (Ch. 0+000 to Ch. 18+461) (Sohna-Gurugram Road (NH-248A) near Alipur Village and ending before KMP Expressway)18.5OpenFeb 2023–––
Vadodara Mumbai Expressway Section of NE-4 Package IV13.0OpenApr 2024–––
Delhi - Vadodara (starting from Hardeoganj Village near Indergarh to Major Bridge on Maj River (Ch. 319.40 to 331.030), NE-4 (Package-11)11.6OpenNov 2023–––
Construction 8-lane access controlled Expressway from Km 69.700 to Km 79.783(Bhoj to Morbe -Spur) Section of VME, Package-XVII on HAM basis.10.084% built–Jul 2025Mar 20268 months
Delhi - Vadodara [Junction with NH-12 to Start of Bridge near Manoharpura] (Ch 419.00 to 427.30), NE-4 (Package-15]8.390% built–Jan 2024Mar 202627 months
Construction 8-lane access controlled Expressway from km. 38.200 to 45.200 (Borivali to sange Secton - SPUR of VME), Package-XVA on HAM basis.7.088% built–Mar 2024Mar 202624 months