Delhi-Mumbai Expressway
NE-4. The first package in the ministry's list opened in Mar 2022, the latest in Jan 2026. 18 packages were still being built on 11 Feb 2026.
- Open, in 22 packages
- 872.8 km
- Being built, in 18 packages
- 435.7 km
- Built so far on unfinished packages, weighted by length
- 78%
- Unfinished packages behind their first target
- 17 of 18
Opened
- 10 Mar 2022Package 6, 31.2 kmDelhi-Vadodara 8-lane carriageway starting at Junction with Keshopura Road to Junction with NH-11 (km 151+84 to 183+0) Green Filed Alignment under BM, NE-4 (Package-6)
- 26 Jun 2022Package 04, 36.9 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-04) (Ch. 78+800 to Ch. 115+700) (HR/Rajasthan Border to Junction with SH-44)
- 28 Jun 2022Package 05, 36.1 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-05) (Ch.115+700 to Ch. 151+840) (Junction atSH-44 to Junction Keshopura road)
- 30 Jun 2022Package 7, 31.3 kmDelhi-Vadodara 8-lane carriageway starting near Junction with NH-11 to start of ROB near junction with NH-11A (km 183 to 214.26) NE-4 (Package-7)
- 3 Aug 2022Package I, 23.7 kmVadodara Mumbai Expressway Section of NE-4 Package I
- 6 Feb 2023Package 8, 33.1 kmDelhi-Vadodara 8-lane carriageway (km 214.26 to 247.31) Green Filed Alignment under BM, NE-4 (Package-8)
- 10 Feb 2023Package 01, 18.5 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-01) (Ch. 0+000 to Ch. 18+461) (Sohna-Gurugram Road (NH-248A) near Alipur Village and ending before KMP Expressway)
- 10 Feb 2023Package 02, 28.5 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-02) (Ch. 18+500 to Ch. 47+000)(Expressway starting before KMP Expressway and ending at Ch. 47+000 near Khanpur Ghati)
- 10 Feb 2023Package 03, 31.8 kmDelhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-03) (Ch. 47+000 to Ch. 78+800) (starting near Khanpur Ghati and ending at HR/RJ Border)
- 16 May 2023Package 29, 22.5 kmDelhi Vadodara Expressway Section of NE-4 Package-29
- 20 Sep 2023Delhi-Mumbai Expressway-MP Portion (NE-4), 244.5 kmDelhi-Mumbai Expressway-MP Portion (NE-4)
- 30 Nov 2023Package 11, 11.6 kmDelhi - Vadodara (starting from Hardeoganj Village near Indergarh to Major Bridge on Maj River (Ch. 319.40 to 331.030), NE-4 (Package-11)
- 30 Dec 2023Package 16, 25.1 kmDelhi-Vadodara (Start of Bridge near Manoharpur to Rajasthan/MP Border (km. 427.3 to 452.425), NE-4 (Package-16)
- 31 Dec 2023Package 9, 45.6 kmDelhi-Vadodara 8-lane carriageway (km 247.31 to 292.95) Green Filed Alignment under BM, NE-4 (Package-9)
- 9 Jan 2024Package II, 32.0 kmVadodara Mumbai Expressway Section of NE-4 Package II
- 10 Jan 2024Package III, 31.0 kmVadodara Mumbai Expressway Section of NE-4 Package III
- 2 Apr 2024Package IV, 13.0 kmVadodara Mumbai Expressway Section of NE-4 Package IV
- 21 May 2024Package 12, 28.1 kmDelhi - Vadodara (starting near Major Bridge on Mej River - Junction on SH-37A (Ch. 331.030 to 359.170), NE-4 (Package-12)
- 28 Jul 2024Package 13, 29.3 kmDelhi - Vadodara (Junction with SH-37A to Junction with NH- 76 (km. 359.170 to 388.42), NE-4 (Package-13)
- 31 Dec 2024Package 14, 30.6 kmDelhi - Vadodara (Junction with NH- 76 to Junction with NH-12 near village Ummedpura) (Ch 388.42 to Ch. 419), NE-4 (Package-14)
- 1 Jun 20254-lane Green Field Expressway Spur from Delhi-…, 66.9 km4-lane Green Field Expressway Spur from Delhi-Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Ph-I in Rajasthan (HAM) NE-4C
- 9 Jan 2026Package 30, 21.5 kmDelhi Vadodara Expressway Section of NE-4 Package-30
Being built
- First target date
- Date given in February 2026
- Answer date, 11 Feb 2026
2021202220232024202520262027
- Package V95% built, 25 kmFirst target Oct 2021. Now expected Mar 2026.
- Package 3195% built, 19 kmFirst target May 2023. Now expected Feb 2026.
- Package 1095% built, 26 kmFirst target May 2023. Now expected Mar 2026.
- Package VII97% built, 28 kmFirst target Nov 2023. Now expected Dec 2024.
- Package 2896% built, 25 kmFirst target Nov 2023. Now expected Mar 2026.
- Package VI99% built, 37 kmFirst target Dec 2023. Now expected Nov 2024.
- Package 1590% built, 8 kmFirst target Jan 2024. Now expected Mar 2026.
- Package XIII91% built, 27 kmFirst target Feb 2024. Now expected Mar 2026.
- Package 2794% built, 26 kmFirst target Feb 2024. Now expected Feb 2026.
- Package X36% built, 25 kmFirst target Mar 2024. Now expected Nov 2026.
- Package XII98% built, 26 kmFirst target Mar 2024. Now expected Feb 2026.
- Package XVA88% built, 7 kmFirst target Mar 2024. Now expected Mar 2026.
- Package XI100% built, 26 kmFirst target May 2024. Now expected Feb 2026.
- Package 2672% built, 33 kmFirst target Aug 2024. Now expected Mar 2026.
- Package XVI93% built, 25 kmFirst target Oct 2024. Now expected Mar 2026.
- Package XVII84% built, 10 kmFirst target Jul 2025. Now expected Mar 2026.
- Package IX22% built, 27 kmFirst target Oct 2025. Now expected Jun 2026.
- Package VIII5% built, 35 kmFirst target Mar 2026. No expected date given.no new date given
Every package
| Delhi-Mumbai Expressway-MP Portion (NE-4) | 244.5 | Open | Sep 2023 | – | – | – |
| 4-lane Green Field Expressway Spur from Delhi-Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Ph-I in Rajasthan (HAM) NE-4C | 66.9 | Open | Jun 2025 | – | – | – |
| Delhi-Vadodara 8-lane carriageway (km 247.31 to 292.95) Green Filed Alignment under BM, NE-4 (Package-9) | 45.6 | Open | Dec 2023 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package VI | 36.9 | 99% built | – | Dec 2023 | Nov 2024 | 12 months |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-04) (Ch. 78+800 to Ch. 115+700) (HR/Rajasthan Border to Junction with SH-44) | 36.9 | Open | Jun 2022 | – | – | – |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-05) (Ch.115+700 to Ch. 151+840) (Junction atSH-44 to Junction Keshopura road) | 36.1 | Open | Jun 2022 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package VIII | 35.4 | 5% built | – | Mar 2026 | Not given | – |
| Delhi-Vadodara 8-lane carriageway (km 214.26 to 247.31) Green Filed Alignment under BM, NE-4 (Package-8) | 33.1 | Open | Feb 2023 | – | – | – |
| Delhi Vadodara Expressway Section of NE-4 Package-26 | 32.8 | 72% built | – | Aug 2024 | Mar 2026 | 19 months |
| Vadodara Mumbai Expressway Section of NE-4 Package II | 32.0 | Open | Jan 2024 | – | – | – |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-03) (Ch. 47+000 to Ch. 78+800) (starting near Khanpur Ghati and ending at HR/RJ Border) | 31.8 | Open | Feb 2023 | – | – | – |
| Delhi-Vadodara 8-lane carriageway starting near Junction with NH-11 to start of ROB near junction with NH-11A (km 183 to 214.26) NE-4 (Package-7) | 31.3 | Open | Jun 2022 | – | – | – |
| Delhi-Vadodara 8-lane carriageway starting at Junction with Keshopura Road to Junction with NH-11 (km 151+84 to 183+0) Green Filed Alignment under BM, NE-4 (Package-6) | 31.2 | Open | Mar 2022 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package III | 31.0 | Open | Jan 2024 | – | – | – |
| Delhi - Vadodara (Junction with NH- 76 to Junction with NH-12 near village Ummedpura) (Ch 388.42 to Ch. 419), NE-4 (Package-14) | 30.6 | Open | Dec 2024 | – | – | – |
| Delhi - Vadodara (Junction with SH-37A to Junction with NH- 76 (km. 359.170 to 388.42), NE-4 (Package-13) | 29.3 | Open | Jul 2024 | – | – | – |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-02) (Ch. 18+500 to Ch. 47+000)(Expressway starting before KMP Expressway and ending at Ch. 47+000 near Khanpur Ghati) | 28.5 | Open | Feb 2023 | – | – | – |
| Delhi - Vadodara (starting near Major Bridge on Mej River - Junction on SH-37A (Ch. 331.030 to 359.170), NE-4 (Package-12) | 28.1 | Open | May 2024 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package VII | 27.5 | 97% built | – | Nov 2023 | Dec 2024 | 14 months |
| Construction 8-lane access controlled Expressway from km. 26.582 to 50.70 of Main Expressway and km.0 to 3 of SPUR (Shirsad to Masvan section of VME), Package-XIII on HAM basis. | 27.2 | 91% built | – | Feb 2024 | Mar 2026 | 26 months |
| Vadodara Mumbai Expressway Section of NE-4 Package IX | 26.6 | 22% built | – | Oct 2025 | Jun 2026 | 9 months |
| Delhi - Vadodara [End of Interchange on NH-166 near village Mui to Hardeoganj village near Indergarh (Ch 292.95 to 319.40), NE-4 (Package-10] | 26.5 | 95% built | – | May 2023 | Mar 2026 | 34 months |
| Construction of 8-lane access controlled Expressway from km. 77 to 103.400 (Ganjad to Talasari section of VME), Package-XI on HAM basis. | 26.4 | 100% built | – | May 2024 | Feb 2026 | 21 months |
| Delhi Vadodara Expressway Section of NE-4 Package-27 | 26.4 | 94% built | – | Feb 2024 | Feb 2026 | 25 months |
| Construction 8-lane access controlled Expressway from km. 50.700 to 77 (Masvan to Ganjad section of VME), Package-XII on HAM basis. | 26.3 | 98% built | – | Mar 2024 | Feb 2026 | 23 months |
| Delhi Vadodara Expressway Section of NE-4 Package-28 | 25.2 | 96% built | – | Nov 2023 | Mar 2026 | 29 months |
| Delhi-Vadodara (Start of Bridge near Manoharpur to Rajasthan/MP Border (km. 427.3 to 452.425), NE-4 (Package-16) | 25.1 | Open | Dec 2023 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package X | 24.6 | 36% built | – | Mar 2024 | Nov 2026 | 32 months |
| Construction of 8-lane access controlled Expressway from km. 45.200 to 69.800 (Amne to Bhoj section - SPUR of VME) basis, Package-XVI on HAM basis. | 24.6 | 93% built | – | Oct 2024 | Mar 2026 | 17 months |
| Vadodara Mumbai Expressway Section of NE-4 Package V | 24.6 | 95% built | – | Oct 2021 | Mar 2026 | 53 months |
| Vadodara Mumbai Expressway Section of NE-4 Package I | 23.7 | Open | Aug 2022 | – | – | – |
| Delhi Vadodara Expressway Section of NE-4 Package-29 | 22.5 | Open | May 2023 | – | – | – |
| Delhi Vadodara Expressway Section of NE-4 Package-30 | 21.5 | Open | Jan 2026 | – | – | – |
| Delhi Vadodara Expressway Section of NE-4 Package-31 | 19.5 | 95% built | – | May 2023 | Feb 2026 | 33 months |
| Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-01) (Ch. 0+000 to Ch. 18+461) (Sohna-Gurugram Road (NH-248A) near Alipur Village and ending before KMP Expressway) | 18.5 | Open | Feb 2023 | – | – | – |
| Vadodara Mumbai Expressway Section of NE-4 Package IV | 13.0 | Open | Apr 2024 | – | – | – |
| Delhi - Vadodara (starting from Hardeoganj Village near Indergarh to Major Bridge on Maj River (Ch. 319.40 to 331.030), NE-4 (Package-11) | 11.6 | Open | Nov 2023 | – | – | – |
| Construction 8-lane access controlled Expressway from Km 69.700 to Km 79.783(Bhoj to Morbe -Spur) Section of VME, Package-XVII on HAM basis. | 10.0 | 84% built | – | Jul 2025 | Mar 2026 | 8 months |
| Delhi - Vadodara [Junction with NH-12 to Start of Bridge near Manoharpura] (Ch 419.00 to 427.30), NE-4 (Package-15] | 8.3 | 90% built | – | Jan 2024 | Mar 2026 | 27 months |
| Construction 8-lane access controlled Expressway from km. 38.200 to 45.200 (Borivali to sange Secton - SPUR of VME), Package-XVA on HAM basis. | 7.0 | 88% built | – | Mar 2024 | Mar 2026 | 24 months |