Ujjain-Garoth Expressway

No package had opened when the ministry answered. 1 package was still being built on 11 Feb 2026.

Being built, in 1 package
136.5 km
Built so far on unfinished packages, weighted by length
99%
Unfinished packages behind their first target
1 of 1

Being built

Ujjain-Garoth Expressway packages being built, first target and expected date
  • First target date
  • Date given in February 2026
  • Answer date, 11 Feb 2026
20232024202520262027
  1. Ujjain-Garoth Partial Expressway (NH-752D)99% built, 137 kmFirst target Dec 2023. Now expected Sep 2025.

Every package

Ujjain-Garoth Expressway packages
Ujjain-Garoth Partial Expressway (NH-752D)136.599% built–Dec 2023Sep 202520 months