Kanpur-Lucknow Expressway
No package had opened when the ministry answered. 2 packages were still being built on 11 Feb 2026.
- Being built, in 2 packages
- 62.8 km
- Built so far on unfinished packages, weighted by length
- 98%
- Unfinished packages behind their first target
- 2 of 2
Being built
- First target date
- Date given in February 2026
- Answer date, 11 Feb 2026
202520262027
- Package II100% built, 45 kmFirst target May 2025. Now expected Feb 2026.
- Package 194% built, 18 kmFirst target Jul 2025. Now expected Mar 2026.
Every package
| 6L Greenfield Kanpur - Lucknow (Expressway) Package II from km. 28.500 to km. 73.744 | 45.2 | 100% built | – | May 2025 | Feb 2026 | 10 months |
| 6L Elevated Kanpur - Lucknow (Expressway) Package-1 from Km. 10+980 to Km. 28+500 | 17.5 | 94% built | – | Jul 2025 | Mar 2026 | 8 months |
Sources2
- Rajya Sabha: Project-wise Details of Completed and Commissioned Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page
- Rajya Sabha: Project-wise Details of Commissioning of Ongoing Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page