Delhi-Amritsar-Katra Expressway
NE-5. The first package in the ministry's list opened in May 2024, the latest in Sep 2024. 18 packages were still being built on 11 Feb 2026.
- Open, in 2 packages
- 59.5 km
- Being built, in 18 packages
- 580.0 km
- Built so far on unfinished packages, weighted by length
- 69%
- Unfinished packages behind their first target
- 12 of 18
Opened
- 21 May 2024Package 3, 30.6 kmDelhi Amritsar Katra Package-3
- 25 Sep 2024Package 4, 28.9 kmDelhi Amritsar Katra Package-4
Being built
- First target date
- Date given in February 2026
- Answer date, 11 Feb 2026
2023202420252026202720282029
- Package 1100% built, 34 kmFirst target Dec 2023. Now expected Nov 2025.
- Package 2100% built, 27 kmFirst target Jan 2024. Now expected Dec 2024.
- Package 695% built, 31 kmFirst target May 2024. No expected date given.no new date given
- Package 599% built, 38 kmFirst target May 2024. Now expected Feb 2026.
- Package 795% built, 37 kmFirst target Jul 2024. Now expected Mar 2026.
- Package 1063% built, 40 kmFirst target Jul 2024. No expected date given.no new date given
- Package 971% built, 43 kmFirst target Jul 2024. Now expected Jun 2026.
- Package 1481% built, 45 kmFirst target Sep 2024. Now expected May 2026.
- Package 1589% built, 35 kmFirst target Sep 2024. Now expected Jul 2026.
- Package 1692% built, 20 kmFirst target Sep 2024. Now expected Jun 2026.
- Amritsar spur 330% built, 28 kmFirst target Oct 2024. Now expected Nov 2026.
- Package 1143% built, 43 kmFirst target Nov 2024. No expected date given.no new date given
- Package 831% built, 35 kmFirst target Mar 2025. No expected date given.no new date given
- Package 1754% built, 27 kmFirst target Jun 2025. Now expected Sep 2026.
- Package 1852% built, 15 kmFirst target Nov 2025. Now expected Aug 2026.
- Amritsar spur 129% built, 17 kmFirst target Apr 2026. Now expected Mar 2028.
- Package 1226% built, 35 kmFirst target Feb 2027. Now expected Feb 2027.
- Amritsar spur 2no progress given, 31 kmNo first target given. No expected date given.no new date given
Every package
| Delhi-Amritsar-Katra Expressway Package-14 | 44.6 | 81% built | – | Sep 2024 | May 2026 | 20 months |
| Delhi Amritsar Katra Package-9 | 43.0 | 71% built | – | Jul 2024 | Jun 2026 | 23 months |
| Delhi Amritsar Katra Package-11 | 43.0 | 43% built | – | Nov 2024 | Not given | – |
| Delhi Amritsar Katra Package-10 | 39.5 | 63% built | – | Jul 2024 | Not given | – |
| Delhi Amritsar Katra Package-5 | 37.7 | 99% built | – | May 2024 | Feb 2026 | 21 months |
| Delhi Amritsar Katra Package-7 | 36.9 | 95% built | – | Jul 2024 | Mar 2026 | 21 months |
| Delhi Amritsar Katra Package-12 | 35.3 | 26% built | – | Feb 2027 | Feb 2027 | On time |
| Delhi-Amritsar-Katra Expressway Package-15 | 35.2 | 89% built | – | Sep 2024 | Jul 2026 | 22 months |
| Delhi Amritsar Katra Package-8 | 35.1 | 31% built | – | Mar 2025 | Not given | – |
| Delhi Amritsar Katra Package-1 | 34.0 | 100% built | – | Dec 2023 | Nov 2025 | 22 months |
| Delhi Amritsar Katra Package-6 | 30.9 | 95% built | – | May 2024 | Not given | – |
| Delhi Amritsar Katra Package-3 | 30.6 | Open | May 2024 | – | – | – |
| Delhi Amritsar Katra (Amritsar Connectivity) Spur-2 | 30.5 | Being built | – | – | Not given | – |
| Delhi Amritsar Katra Package-4 | 28.9 | Open | Sep 2024 | – | – | – |
| Delhi Amritsar Katra (Amritsar Connectivity) Spur-3 | 28.1 | 30% built | – | Oct 2024 | Nov 2026 | 25 months |
| Delhi-Amritsar-Katra Expressway Package-17 | 26.8 | 54% built | – | Jun 2025 | Sep 2026 | 15 months |
| Delhi Amritsar Katra Package-2 | 26.8 | 100% built | – | Jan 2024 | Dec 2024 | 11 months |
| Delhi-Amritsar-Katra Expressway Package-16 | 20.4 | 92% built | – | Sep 2024 | Jun 2026 | 21 months |
| Delhi Amritsar Katra (Amritsar Connectivity) Spur-1 | 16.9 | 29% built | – | Apr 2026 | Mar 2028 | 24 months |
| Delhi-Amritsar-Katra Expressway Package-18 | 15.3 | 52% built | – | Nov 2025 | Aug 2026 | 9 months |
Sources2
- Rajya Sabha: Project-wise Details of Completed and Commissioned Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page
- Rajya Sabha: Project-wise Details of Commissioning of Ongoing Expressway Works on National Highways (NHs) (In relpy to Unstarred Question as on 11th February 2026), on data.gov.indata.gov.inPublisher page