Delhi-Amritsar-Katra Expressway

NE-5. The first package in the ministry's list opened in May 2024, the latest in Sep 2024. 18 packages were still being built on 11 Feb 2026.

Open, in 2 packages
59.5 km
Being built, in 18 packages
580.0 km
Built so far on unfinished packages, weighted by length
69%
Unfinished packages behind their first target
12 of 18

Opened

  1. 21 May 2024Package 3, 30.6 kmDelhi Amritsar Katra Package-3
  2. 25 Sep 2024Package 4, 28.9 kmDelhi Amritsar Katra Package-4

Being built

Delhi-Amritsar-Katra Expressway packages being built, first target and expected date
  • First target date
  • Date given in February 2026
  • Answer date, 11 Feb 2026
2023202420252026202720282029
  1. Package 1100% built, 34 kmFirst target Dec 2023. Now expected Nov 2025.
  2. Package 2100% built, 27 kmFirst target Jan 2024. Now expected Dec 2024.
  3. Package 695% built, 31 kmFirst target May 2024. No expected date given.no new date given
  4. Package 599% built, 38 kmFirst target May 2024. Now expected Feb 2026.
  5. Package 795% built, 37 kmFirst target Jul 2024. Now expected Mar 2026.
  6. Package 1063% built, 40 kmFirst target Jul 2024. No expected date given.no new date given
  7. Package 971% built, 43 kmFirst target Jul 2024. Now expected Jun 2026.
  8. Package 1481% built, 45 kmFirst target Sep 2024. Now expected May 2026.
  9. Package 1589% built, 35 kmFirst target Sep 2024. Now expected Jul 2026.
  10. Package 1692% built, 20 kmFirst target Sep 2024. Now expected Jun 2026.
  11. Amritsar spur 330% built, 28 kmFirst target Oct 2024. Now expected Nov 2026.
  12. Package 1143% built, 43 kmFirst target Nov 2024. No expected date given.no new date given
  13. Package 831% built, 35 kmFirst target Mar 2025. No expected date given.no new date given
  14. Package 1754% built, 27 kmFirst target Jun 2025. Now expected Sep 2026.
  15. Package 1852% built, 15 kmFirst target Nov 2025. Now expected Aug 2026.
  16. Amritsar spur 129% built, 17 kmFirst target Apr 2026. Now expected Mar 2028.
  17. Package 1226% built, 35 kmFirst target Feb 2027. Now expected Feb 2027.
  18. Amritsar spur 2no progress given, 31 kmNo first target given. No expected date given.no new date given

Every package

Delhi-Amritsar-Katra Expressway packages
Delhi-Amritsar-Katra Expressway Package-1444.681% built–Sep 2024May 202620 months
Delhi Amritsar Katra Package-943.071% built–Jul 2024Jun 202623 months
Delhi Amritsar Katra Package-1143.043% built–Nov 2024Not given–
Delhi Amritsar Katra Package-1039.563% built–Jul 2024Not given–
Delhi Amritsar Katra Package-537.799% built–May 2024Feb 202621 months
Delhi Amritsar Katra Package-736.995% built–Jul 2024Mar 202621 months
Delhi Amritsar Katra Package-1235.326% built–Feb 2027Feb 2027On time
Delhi-Amritsar-Katra Expressway Package-1535.289% built–Sep 2024Jul 202622 months
Delhi Amritsar Katra Package-835.131% built–Mar 2025Not given–
Delhi Amritsar Katra Package-134.0100% built–Dec 2023Nov 202522 months
Delhi Amritsar Katra Package-630.995% built–May 2024Not given–
Delhi Amritsar Katra Package-330.6OpenMay 2024–––
Delhi Amritsar Katra (Amritsar Connectivity) Spur-230.5Being built––Not given–
Delhi Amritsar Katra Package-428.9OpenSep 2024–––
Delhi Amritsar Katra (Amritsar Connectivity) Spur-328.130% built–Oct 2024Nov 202625 months
Delhi-Amritsar-Katra Expressway Package-1726.854% built–Jun 2025Sep 202615 months
Delhi Amritsar Katra Package-226.8100% built–Jan 2024Dec 202411 months
Delhi-Amritsar-Katra Expressway Package-1620.492% built–Sep 2024Jun 202621 months
Delhi Amritsar Katra (Amritsar Connectivity) Spur-116.929% built–Apr 2026Mar 202824 months
Delhi-Amritsar-Katra Expressway Package-1815.352% built–Nov 2025Aug 20269 months