Namma Metro

Bengaluru. Run by Bangalore Metro Rail Corporation (BMRCL).

Running
96.1 km
Being built
121.1 km
First opened
20 Oct 2011
Riders a day, 2024-25
7.98 lakh
Running 96.1 kmBeing built 121.1 kmProposed 37 km

BMRCL reports 96.10 km in service: 49.59 km east-west, 27.36 km north-south, and the 19.15 km Yellow Line. Under construction is the ministry's 121.13 km: Phase 2, 2A and 2B balance and the 44.65 km Phase 3, which reported 3.60% physical progress in June 2026. The Pink Line counts as open only once passenger service is official.

Route km in the ministry's tables

Operational length the Housing and Urban Affairs ministry printed for Bengaluru in Lok Sabha answers. Its table of February 2026 also gives 121.1 km under construction.

  1. 7421 Dec 2023
  2. 7727 Mar 2025
  3. 96.118 Dec 2025
  4. 96.15 Feb 2026

Riders a day

Average riders a day in each financial year, in lakh, from a Lok Sabha answer of February 2026.

  1. 3.482021-22
  2. 5.312022-23
  3. 7.082023-24
  4. 7.982024-25
  5. 8.972025-26*, Till Dec, 2025

* Till Dec, 2025

Being built

Physical progress at 30 Jun 2026 and sanctioned cost, from a Lok Sabha answer.

  1. Phase-295.7%

    72.1 km, ₹26,405 cr

  2. Phase-2A & 2B72.8%

    58.2 km, ₹14,788 cr

  3. Phase-33.6%

    44.6 km, ₹15,611 cr

Approved projects

Projects the Union government sanctioned, with the length, cost and the daily riders their detailed project report forecast, where the ministry published one.

  • Phase 3

    44.6 km, ₹15,611 cr, ₹350 cr a km. Forecast 6,35,000 riders a day by 2028

  • Phase 2A & 2B

    58.2 km, ₹14,788 cr, ₹254 cr a km. Forecast 7,71,000 riders a day by 2025

Sections opened

Sections the ministry lists as opened in the financial years 2018-19 to 2023-24, and in the calendar year 2025.

2020-21

Yelachenahalli to Silk Institute, 6.1 km

2021-22

Mysore Road Station to Kengeri Station, 7.5 km

2022-23

KR Pura to Whitefield, 13.7 km

2023-24

Krishnarajapura to Baiyappanahalli, 2.1 km

Kengeri to Challaghatta, 2 km

2025

Bangalore Metro, 19.1 km

Revenue

Revenue in ₹ crore each financial year, as the ministry gave it to the Lok Sabha.

  1. 872020-21
  2. 2072021-22
  3. 7852022-23
  4. 9902023-24
  5. 1,1912024-25

Operator accounts

From each operator's standalone audited accounts, in ₹ crore. Income can include outside project work and grants.

Bangalore Metro Rail Corporation Limited

50:50 joint venture. Income includes ₹255 crore of non-cash unwinding on interest-free debt, and State reimbursement of cash losses from 2017-18 to 2019-20. Foreign exchange on loans adds ₹256 crore to 2024-25 interest and cut 2023-24's by ₹278 crore. Debt is shown from 2022-23, when reported borrowings fall by more than half. CAG says BMRCL made cash losses every year from 2013-14 to 2021-22 and depended on Karnataka to service its debt.

YearIncomeFaresBefore interest and depreciationNet resultDebt
2024-251,191754485−62517,707
2023-24990574376−34314,895
2022-23785423298−64211,378
2021-22229163−117−456–
2020-218749−207−912–
2019-2047637797−599–
2018-19536355200−498–
2017-18539281277−352–
2016-17145110−27−458–
2015-165428−79−361–
2014-1543––––

Central money released

Equity, pass-through loans and grants from the Housing and Urban Affairs ministry, in ₹ crore, from a Lok Sabha answer of April 2026.

  1. 1,8582020-21
  2. 3,6232021-22
  3. 4,0422022-23
  4. 3,6172023-24
  5. 4,8152024-25
  6. 1,6932025-26*, to 2026-03-30

* to 2026-03-30