Metro rail in India
1,159 km of metro and regional rail run in 26 cities, 4.7 times the network of 2014. Delhi and NCR has the most running. The most being built is in Delhi and NCR, Mumbai and Bengaluru.
- running in 26 cities, Parliament reply of 20 Jul 2026
- 1,159 km
- running in 26 cities, Parliament reply of 20 Jul 2026
- sanctioned and not yet open, per the minister on 23 Oct 2026
- 998 km
- sanctioned and not yet open, per the minister on 23 Oct 2026
- rides a day, 31 Mar 2026
- 1.15 crore
- rides a day, 31 Mar 2026
- the 248 km in 5 cities in 2014
- 4.7×
- the 248 km in 5 cities in 2014
Route km by city in the ministry's table of 5 Feb 2026
- Delhi and NCR396 km running, 158 km being built
- Mumbai111 km running, 141 km being built
- Bengaluru96 km running, 121 km being built
- Chennai54 km running, 119 km being built
- Kolkata73 km running, 60 km being built
- Pune33 km running, 78 km being built
- Nagpur40 km running, 44 km being built
- Namo Bharat55 km running, 27 km being built
- Hyderabad69 km
- Ahmedabad68 km
- Suratbeing built only, 40 km
- Kochi28 km running, 11 km being built
- Lucknow23 km running, 11 km being built
- Patna3 km running, 30 km being built
- Kanpur15 km running, 17 km being built
- Indore6 km running, 25 km being built
- Agra6 km running, 24 km being built
- Thanebeing built only, 29 km
- Bhopal7 km running, 21 km being built
- Jaipur12 km
Being built is from the same table, 5 Feb 2026: 957 km in all. Delhi and NCR includes Noida, Gurugram and the other NCR towns.
Network by city
The ministry's tables went from 905 km on 21 Dec 2023 to 1,096 km on 5 Feb 2026. 16 of 18 places added track in that time.
Riders
Delhi carried 69.16 lakh riders a day in 2024-25, against 18.6 lakh for the other 8 systems in the list together.
Being built
30 projects with 886 km of line. 11 are more than half built, and 6 have only preliminary works.
- Pune Line 3 (Maan-Hinjawadi-Shivajinagar)95.7%
23.2 km, ₹6,124 cr
- Bengaluru Phase-295.7%
72.1 km, ₹26,405 cr
- Delhi Phase IV (03 Priority Corridors)82.2%
65.2 km, ₹24,949 cr
- Kanpur Metro82%
32.4 km, ₹11,076 cr
- Surat Metro81.1%
40.4 km, ₹12,020 cr
- Bengaluru Phase-2A & 2B72.8%
58.2 km, ₹14,788 cr
- Agra Metro72%
29.4 km, ₹8,380 cr
- Indore Metro64.2%
31.1 km, ₹7,501 cr
- Bhopal Metro59.9%
30.9 km, ₹6,941 cr
- Chennai Phase 254.6%
118.9 km, ₹63,246 cr
- Patna Metro53%
32.5 km, ₹13,366 cr
- Jaipur Phase 1D49%
1.4 km, ₹222 cr
- Pune Phase-1 Extension (PCMC to Nigdi)47.2%
4.4 km, ₹910 cr
- Nagpur Phase-II40.9%
43.8 km, ₹6,708 cr
- Kochi Phase II39.6%
11.2 km, ₹1,957 cr
- Thane Metro9.5%
29 km, ₹12,200 cr
- Pune Phase-1 Extension (Swargate to Katraj)6.2%
5.5 km, ₹2,955 cr
- Delhi Phase V (A)5.6%
16.1 km, ₹12,015 cr
- Delhi Phase IV (02 Remaining Corridors)4.3%
20.8 km, ₹6,231 cr. The answer prints ₹6,230.99 crore, the same as the Rithala-Kundli row below it. The ministry's list of approvals answered a week later gives ₹8,400 crore for the two remaining corridors.
- Bengaluru Phase-33.6%
44.6 km, ₹15,611 cr
- Gurugram Millennium City Centre to Cyber City Gurugram3.3%
28.5 km, ₹5,453 cr
- Delhi Phase IV Rithala Kundli Corridor3%
26.5 km, ₹6,231 cr
- Pune Phase 2 (Vanaz to Chandni Chowk & Ramwadi to Wagholi)1.9%
12.8 km, ₹3,626 cr
- Pune 2, Line-4 (Kharadi to Khadakwasla)1.3%
31.6 km, ₹9,858 cr
- Noida Extension from Sector 142 to Botanical GardenNot started
11.6 km, ₹2,254 cr. Preliminary works under progress
- Lucknow Phase 1BNot started
11.2 km, ₹5,801 cr. Preliminary works under progress
- Noida Extension Aqua line from Depot Station to Boraki MMTHNot started
2.6 km, ₹416 cr. Preliminary works under progress
- Ahmedabad Phase 2BNot started
3.3 km, ₹1,067 cr. Preliminary works under progress
- Jaipur Phase 2Not started
41 km, ₹13,038 cr. Preliminary works under progress
- Ahmedabad Phase 2ANot started
6 km, ₹2,169 cr. Preliminary works under progress
Cost per km
Projects being built range from ₹153 cr to ₹747 cr a km. Approvals since January 2024 add 383 km at ₹1,59,110 cr, or ₹416 cr a km.
When each system opened
Kolkata ran alone for 18 years. 14 of the 21 systems running today opened in 2017 or later.
Sections opened each year
457 km opened in the 6 financial years from 2018-19 to 2023-24.
- 2018-19210 km
- 2019-2039 km
- 2020-2125 km
- 2021-2232 km
- 2022-23105 km
- 2023-2446 km
- 2025*93 km
Fares against running costs, Delhi
Fares covered running costs in 3 of the 5 years with both figures. In 2024-25 they brought in ₹4,601 crore against ₹4,188 crore spent. The figure above each pair is the gap in ₹ crore.
| Year | Fares, ₹ crore | Operating cost, ₹ crore |
|---|---|---|
| 2016-17 | 2179 | not published |
| 2017-18 | 3027.26 | not published |
| 2018-19 | 3582.8 | not published |
| 2019-20 | 3897.29 | not published |
| 2020-21 | 876.98 | 2638.21 |
| 2021-22 | 1975.99 | 3226.91 |
| 2022-23 | 3633.18 | 3573.31 |
| 2023-24 | 4204.2 | 3832.68 |
| 2024-25 | 4600.62 | 4187.83 |
Operator accounts
15 of the 15 operators reported a net loss in their latest year. Delhi Metro earned ₹4,250 crore in fares in 2025-26 and lost ₹1,389 crore after depreciation and interest, with a surplus of ₹1,868 crore before them.
Delhi Metro, ₹ crore a year, 2014-15 to 2025-26
| 2025-26 | ₹4,250 cr | ₹8,448 cr | ₹638 cr | -₹1,389 cr | |
| 2024-25 | ₹754 cr | ₹1,191 cr | ₹652 cr | -₹625 cr | |
| 2024-25 | – | ₹1,113 cr | ₹940 cr | -₹626 cr | |
| 2024-25 | ₹118 cr | ₹787 cr | ₹311 cr | -₹369 cr | |
| 2024-25 | ₹290 cr | ₹624 cr | ₹160 cr | -₹1,003 cr | |
| 2024-25 | ₹48 cr | ₹386 cr | ₹265 cr | -₹550 cr | |
| 2024-25 | ₹80 cr | ₹383 cr | ₹320 cr | -₹625 cr | |
| 2025-26 | ₹103 cr | ₹382 cr | ₹1,403 cr | -₹1,451 cr | |
| 2023-24 | ₹286 cr | ₹341 cr | – | -₹465 cr | |
| 2024-25 | ₹61 cr | ₹286 cr | ₹23 cr | -₹55 cr | |
| 2024-25 | ₹112 cr | ₹275 cr | ₹342 cr | -₹431 cr | |
| 2024-25 | ₹9 cr | ₹176 cr | ₹9 cr | -₹357 cr | |
| 2024-25 | ₹30 cr | ₹171 cr | ₹30 cr | -₹67 cr | |
| 2024-25 | – | ₹68 cr | ₹0 cr | -₹1 cr | |
| 2025-26 | – | – | – | -₹1,277 cr |
Not in this table: Maha Mumbai Metro Operation Corporation Limited, Patna Metro Rail Corporation Limited, Rapid Metro Gurugram (HMRTC), Kochi Water Metro Limited, Pune IT City Metro Rail Limited.
Central money released
₹1,37,119 cr across 19 agencies in 6 years, 2020-21 to 2025-26. Namo Bharat got the most: ₹20,967 cr.
- Namo Bharat
- Bengaluru
- Delhi
- Chennai
- Mumbai Line 3
- Surat
- Others
How the running total adds up
The system rows, with Namo Bharat and the Monorail added, come to 1,186 km, against the minister's 1,185 km.
- 21 systems with passenger service1,131 km
- Namo Bharat, beyond the track shared with Meerut Metro+59 km
- Mumbai Monorail, counted by the ministry+20 km
- Pune Line 3, opened 3 Nov 2026 after the statement−23 km
- Comparable sum1,186 km
- Minister of State, 23 Oct 2026over 1,185 km
- Parliament reply, 20 Jul 20261,159 km
- Official figure, 31 Mar 20261,155 km
How the being-built total adds up
57 km of the minister's 998 km has no published breakdown.
- 17 system rows816 km
- Sanctioned, only preliminary works: Jaipur Phase 2, Lucknow 1B, Noida, Ahmedabad, Mumbai Line 10+85 km
- Kolkata, the Housing ministry's table against the Railways' itemised list+8 km
- Pune Line 3, still unopened at the minister's statement+23 km
- Mumbai Lines 5 and 5A, 34.2 km now approved against 24.9 km in ministry tables (secondary)+9 km
- Reconciled941 km
- No published breakdown57 km
- Minister of State, 23 Oct 2026998 km
Systems and projects tracked
32 systems and projects, from running lines to proposals.
- Running1,131 km
- Being built816 km
- Approved, work not evidenced97 km
- Proposed1,113 km
Opening next
- SuratDream City to Althan stretch, reported target, Nov 2026
- DelhiGolden Line (Aerocity to Tughlakabad) partial opening, Dec 2026
- MumbaiLine 4 and 4A, Gaimukh to Cadbury Junction, partial opening, Dec 2026
- KolkataOrange Line full New Garia-Airport corridor; Yellow Line Noapara-New Barrackpore extension, Dec 2026
- KochiPhase 2 Pink Line opens, 2027
- KanpurCorridor 1 completion + Corridor 2 start, 2027
- BhopalPhase 1 full corridor opens, 2027
- AgraFull Phase 1 corridor opens, 2027
- PatnaMithapur to Khemnichak elevated section (3.1 km), Jun 2027
- ThaneProject completion target, 2029
- IndoreRadisson Square to Airport section of the Yellow Line, 2030
Sources116
- Rajya Sabha Q 66, Jul 2026: about 1,159 km including RRTS in 26 citiessansad.inPDF document
- Lok Sabha Q 1943, Jul 2026: sanction datessansad.inPDF document
- Lok Sabha starred question 270, Length of Metro Rail Network, answered 2023-12-21sansad.inPDF document
- Lok Sabha unstarred question 4460, Metro Rail Network, answered 2025-03-27sansad.inPDF document
- Lok Sabha Q 3110, Dec 2025: metro networksansad.inPDF document
- Lok Sabha Q 1054, Feb 2026: city-wise metro networksansad.inPDF document