Patna Metro

Patna. Run by Patna Metro Rail Corp. (PMRC); operations by DMRC.

Running
6.2 km
Being built
26.3 km
First opened
7 Oct 2025
Running 6.2 kmBeing built 26.3 km

Next: Mithapur to Khemnichak elevated section (3.1 km), Jun 2027. Targets often slip.

Bihar's first metro. The official 2025 inauguration annexure records 2.7 km in operation from the 32.507 km Phase 1 project; the balance is counted as under construction. The priority section was inaugurated on 6 October 2025, with public service from 7 October. Service reached Malahi Pakri on 2 July 2026, taking the Blue Line to 6.2 km; the official annexure has not yet been reissued, so that length rests on press reports.

Route km in the ministry's tables

Operational length the Housing and Urban Affairs ministry printed for Patna in Lok Sabha answers. Its table of February 2026 also gives 29.8 km under construction.

  1. –21 Dec 2023
  2. –27 Mar 2025
  3. 2.718 Dec 2025
  4. 2.75 Feb 2026

Being built

Physical progress at 30 Jun 2026 and sanctioned cost, from a Lok Sabha answer.

  1. Patna Metro Rail Project53%

    32.5 km, ₹13,366 cr

Sections opened

Sections the ministry lists as opened in the financial years 2018-19 to 2023-24, and in the calendar year 2025.

2025

Patna Metro, 2.7 km

Central money released

Equity, pass-through loans and grants from the Housing and Urban Affairs ministry, in ₹ crore, from a Lok Sabha answer of April 2026.

  1. 1632020-21
  2. 502021-22
  3. 4382022-23
  4. 7012023-24
  5. 1012024-25
  6. 1,6172025-26*, to 2026-03-30

* to 2026-03-30