Patna Metro
Patna. Run by Patna Metro Rail Corp. (PMRC); operations by DMRC.
- Running
- 6.2 km
- Being built
- 26.3 km
- First opened
- 7 Oct 2025
Next: Mithapur to Khemnichak elevated section (3.1 km), Jun 2027. Targets often slip.
Bihar's first metro. The official 2025 inauguration annexure records 2.7 km in operation from the 32.507 km Phase 1 project; the balance is counted as under construction. The priority section was inaugurated on 6 October 2025, with public service from 7 October. Service reached Malahi Pakri on 2 July 2026, taking the Blue Line to 6.2 km; the official annexure has not yet been reissued, so that length rests on press reports.
Route km in the ministry's tables
Operational length the Housing and Urban Affairs ministry printed for Patna in Lok Sabha answers. Its table of February 2026 also gives 29.8 km under construction.
- –21 Dec 2023
- –27 Mar 2025
- 2.718 Dec 2025
- 2.75 Feb 2026
Being built
Physical progress at 30 Jun 2026 and sanctioned cost, from a Lok Sabha answer.
- Patna Metro Rail Project53%
32.5 km, ₹13,366 cr
Sections opened
Sections the ministry lists as opened in the financial years 2018-19 to 2023-24, and in the calendar year 2025.
- 2025
Patna Metro, 2.7 km
Central money released
Equity, pass-through loans and grants from the Housing and Urban Affairs ministry, in ₹ crore, from a Lok Sabha answer of April 2026.
- 1632020-21
- 502021-22
- 4382022-23
- 7012023-24
- 1012024-25
- 1,6172025-26*, to 2026-03-30
* to 2026-03-30
Sources11
- DMRC: Patna Metrodelhimetrorail.comPublisher page
- Hindustan Times: Patna Metro expands to Malahi Pakri, 2 July 2026hindustantimes.comPublisher page
- Rajya Sabha: metro sections inaugurated in 2025sansad.inPDF document
- Lok Sabha starred question 270, Length of Metro Rail Network, answered 2023-12-21sansad.inPDF document
- Lok Sabha unstarred question 4460, Metro Rail Network, answered 2025-03-27sansad.inPDF document
- Lok Sabha unstarred question 3110, Metro Rail Network and its Achievements, answered 2025-12-18sansad.inPDF document