Jaipur Metro

Jaipur. Run by Jaipur Metro Rail Corp. (JMRC).

Running
12.1 km
Being built
1.4 km
First opened
3 Jun 2015
Running 12.1 kmBeing built 1.4 kmApproved 41 km

12.1 km operational per the ministry. Phase 1D (1.35 km) was 49% complete in June 2026. The 41 km Phase 2 was approved in April 2026 and its foundation stone laid on 4 July 2026; the ministry reports preliminary works only, so it stays approved.

Route km in the ministry's tables

Operational length the Housing and Urban Affairs ministry printed for Jaipur in Lok Sabha answers.

  1. 1221 Dec 2023
  2. 12.127 Mar 2025
  3. 12.118 Dec 2025
  4. 12.15 Feb 2026

Being built

Physical progress at 30 Jun 2026 and sanctioned cost, from a Lok Sabha answer.

  1. Phase 1D49%

    1.4 km, ₹222 cr

  2. Phase 2Not started

    41 km, ₹13,038 cr. Preliminary works under progress

Approved projects

Projects the Union government sanctioned, with the length, cost and the daily riders their detailed project report forecast, where the ministry published one.

  • Phase II

    41 km, ₹13,038 cr, ₹318 cr a km

  • Phase ID

    1.4 km, ₹222 cr, ₹165 cr a km

Sections opened

Sections the ministry lists as opened in the financial years 2018-19 to 2023-24, and in the calendar year 2025.

2020-21

Chandpole to Badi Choupar, 2.4 km

Operator accounts

From each operator's standalone audited accounts, in ₹ crore. Income can include outside project work and grants.

Jaipur Metro Rail Corporation Limited

Company of the Rajasthan government. Income includes a ₹94 crore State revenue grant: without grants the company reports a ₹46 crore operating loss before depreciation and finance cost. Debt is mostly interest-free State loans at carrying value. 2022-23 shows a profit only because of a ₹223 crore gain on selling land, and the 2023-24 loss includes a ₹44 crore past service charge. 2023-24 is as restated.

YearIncomeFaresBefore interest and depreciationNet resultDebt
2024-251713071−67519
2023-241322537−146536
2022-231321960143496