Bhopal. Run by Madhya Pradesh Metro Rail Corp. (MPMRCL).

Running
6.9 km
Being built
24 km
First opened
20 Dec 2025
Running 6.9 kmBeing built 24 kmProposed 77.1 km

Next: Phase 1 full corridor opens, 2027. Targets often slip.

The 6.94 km Orange Line priority corridor opened on 20 December 2025. The remaining 23.96 km of the 30.90 km project in the ministry's June 2026 table is under construction, at 59.94% physical progress.

Route km in the ministry's tables

Operational length the Housing and Urban Affairs ministry printed for Bhopal in Lok Sabha answers. Its table of February 2026 also gives 20.9 km under construction.

  1. –21 Dec 2023
  2. –27 Mar 2025
  3. –18 Dec 2025
  4. 6.95 Feb 2026

Being built

Physical progress at 30 Jun 2026 and sanctioned cost, from a Lok Sabha answer.

  1. Bhopal Metro Rail Project59.9%

    30.9 km, ₹6,941 cr

Sections opened

Sections the ministry lists as opened in the financial years 2018-19 to 2023-24, and in the calendar year 2025.

2025

MP Metro (Bhopal), 6.9 km

Operator accounts

From each operator's standalone audited accounts, in ₹ crore. Income can include outside project work and grants.

Madhya Pradesh Metro Rail Corporation Limited

50:50 joint venture of the Union and Madhya Pradesh governments. No fare service in these years: Indore opened on 31 May 2025. Income is mostly deposit interest and most project costs go to capital work in progress, so the small loss says nothing yet about running a metro.

YearIncomeFaresBefore interest and depreciationNet resultDebt
2024-2568–5−14,055
2023-2437–2−22,992

Central money released

Equity, pass-through loans and grants from the Housing and Urban Affairs ministry, in ₹ crore, from a Lok Sabha answer of April 2026.

  1. 02020-21
  2. 5272021-22
  3. 2182022-23
  4. 6132023-24
  5. 2162024-25
  6. 1,1602025-26*, to 2026-03-30