Mumbai Metro
Mumbai. Run by MMRDA / MMRC / Maha Mumbai Metro Operation Corp..
- Running
- 91.5 km
- Being built
- 121 km
- First opened
- 8 Jun 2014
Next: Line 4 and 4A, Gaimukh to Cadbury Junction, partial opening, Dec 2026. Targets often slip.
Lines 1, 2A, 7 and the full Aqua Line (Line 3, Cuffe Parade to Aarey, opened October 2025) are operational. Line 2B Phase 1 and Line 9 Phase 1 opened on 7 April 2026, and Line 2B reached Chembur Naka on 13 August 2026. The 91.48 km rests on secondary line tables because no official length exists for those 2026 sections. Under construction is Line 2B balance 16.77, Line 4 32.3, 4A 2.7, 5 24.9, 6 14.5, 9 and 7A balance 8.8, and 12 20.7 km. Approved is Line 10 (9.2 km, the ministry records that construction has not started) and Line 5A (11.83 km, Union approval reported by Indian Infrastructure, no PIB release found). Line 5's own length may be 22.38 km after that approval. Monorail is not included.
Route km in the ministry's tables
Operational length the Housing and Urban Affairs ministry printed for Mumbai in Lok Sabha answers. Its table of February 2026 also gives 141.4 km under construction.
- 7721 Dec 2023
- 88.927 Mar 2025
- 110.618 Dec 2025
- 110.65 Feb 2026
Riders a day
Average riders a day in each financial year, in lakh, from a Lok Sabha answer of February 2026.
Line 3 only. Project is fully operational from Oct, 2025
- 1.62025-26*, Till Dec, 2025
* Till Dec, 2025
Sections opened
Sections the ministry lists as opened in the financial years 2018-19 to 2023-24, and in the calendar year 2025.
- 2022-23
Dahisar (E) to Dahanukarwadi (Phase 1), 9.8 km
Valnai to Andheri(W), 8.8 km
Aarey to Gundavali(E), 5.8 km
Ovaripada/Dahisar (E) to Aarey Colony (Phase 1), 10.7 km
- 2025
Mumbai Metro Line 3, 20.9 km
Revenue
Revenue in ₹ crore each financial year, as the ministry gave it to the Lok Sabha.
Line 3 only
- 1762024-25
Operator accounts
From each operator's standalone audited accounts, in ₹ crore. Income can include outside project work and grants.
Mumbai Metro One Private Limited
Private company, listed-parent subsidiary. From parent Reliance Infrastructure's filing, not MMOPL's own accounts. Turnover ₹427 crore and a net loss of ₹1,277 crore in 2025-26, against ₹380 crore and ₹594 crore a year earlier. Net worth is negative ₹3,957 crore.
| Year | Income | Fares | Before interest and depreciation | Net result | Debt |
|---|---|---|---|---|---|
| 2025-26 | – | – | – | −1,277 | – |
| 2024-25 | – | – | – | −594 | – |
Mumbai Metro Rail Corporation Limited
50:50 joint venture of the Union and Maharashtra governments. Fare service began in October 2024 on part of the line, so 2024-25 holds about six months of ₹9 crore fares. ₹18,630 crore of the project was still capital work in progress at March 2025. The loss includes a ₹140 crore deferred tax charge. 2023-24 is as restated in the 2024-25 accounts.
| Year | Income | Fares | Before interest and depreciation | Net result | Debt |
|---|---|---|---|---|---|
| 2024-25 | 176 | 9 | −41 | −357 | 17,936 |
| 2023-24 | 4 | – | −61 | −96 | 15,517 |
Central money released
Equity, pass-through loans and grants from the Housing and Urban Affairs ministry, in ₹ crore, from a Lok Sabha answer of April 2026.
Mumbai Line 3
- 1,3752020-21
- 2,4122021-22
- 5072022-23
- 3,8952023-24
- 4,4852024-25
- 1,3762025-26*, to 2026-03-30
* to 2026-03-30
Sources15
- Lok Sabha Q 192, Jan 2026: Mumbai region lines and progresssansad.inPDF document
- Indian Infrastructure: Union approves Line 5 and 5A, 34.2 km (secondary)indianinfrastructure.comPublisher page
- MMRDA: Mumbai Metro projectsmmrda.maharashtra.gov.inPublisher page
- Swarajya: Line 2B Diamond Garden to Chembur Naka opens 13 August 2026swarajyamag.comPublisher page
- Lok Sabha starred question 270, Length of Metro Rail Network, answered 2023-12-21sansad.inPDF document
- Lok Sabha unstarred question 4460, Metro Rail Network, answered 2025-03-27sansad.inPDF document