Meerut Metro
Meerut. Run by National Capital Region Transport Corp. (NCRTC).
- Running
- 23.6 km
- Being built
- 0 km
- First opened
- 22 Feb 2026
23.6 km, 13 stations from Modipuram to Meerut South opened 22 February 2026. India's first urban metro sharing tracks and stations with an RRTS corridor (the Delhi–Meerut Namo Bharat).
Operator accounts
From each operator's standalone audited accounts, in ₹ crore. Income can include outside project work and grants.
National Capital Region Transport Corporation Limited
Government joint venture. The Delhi-Meerut corridor was completed in August 2025, so 2025-26 is the first year interest and depreciation on it reach the accounts, giving a ₹1,451 crore loss. Earlier profits arose because operating results went to capital work in progress and revenue from operations was nil.
| Year | Income | Fares | Before interest and depreciation | Net result | Debt |
|---|---|---|---|---|---|
| 2025-26 | 382 | 103 | 172 | −1,451 | 17,037 |
| 2024-25 | 231 | – | – | 77 | 12,805 |
| 2023-24 | 239 | – | – | 139 | 10,151 |