Kochi Metro
Kochi. Run by Kochi Metro Rail Limited (KMRL).
- Running
- 28.5 km
- Being built
- 11.2 km
- First opened
- 19 Jun 2017
- Riders a day, 2024-25
- 0.88 lakh
Next: Phase 2 Pink Line opens, 2027. Targets often slip.
Phase 2 (Pink Line — JLN Stadium to InfoPark/Kakkanad) under construction.
Route km in the ministry's tables
Operational length the Housing and Urban Affairs ministry printed for Kochi in Lok Sabha answers. Its table of February 2026 also gives 11.2 km under construction.
- 2721 Dec 2023
- 28.527 Mar 2025
- 28.518 Dec 2025
- 28.55 Feb 2026
Riders a day
Average riders a day in each financial year, in lakh, from a Lok Sabha answer of February 2026.
- 0.472021-22
- 0.682022-23
- 0.882023-24
- 0.882024-25
- 1.062025-26*, Till Dec. 2025
* Till Dec. 2025
Being built
Physical progress at 30 Jun 2026 and sanctioned cost, from a Lok Sabha answer.
- Phase II39.6%
11.2 km, ₹1,957 cr
Approved projects
Projects the Union government sanctioned, with the length, cost and the daily riders their detailed project report forecast, where the ministry published one.
Phase 1A
2 km, ₹711 cr, ₹355 cr a km. Forecast 46,000 riders a day by 2025
Phase II
11.2 km, ₹1,957 cr, ₹175 cr a km. Forecast 1,13,572 riders a day by 2025
Sections opened
Sections the ministry lists as opened in the financial years 2018-19 to 2023-24, and in the calendar year 2025.
- 2019-20
Maharaja's college to Thykkodam, 5.7 km
- 2020-21
Thykoodam to Petta, 1.3 km
- 2022-23
Petta to SN Junction (Phase 1A), 2 km
Revenue
Revenue in ₹ crore each financial year, as the ministry gave it to the Lok Sabha.
- 1672020-21
- 1422021-22
- 2012022-23
- 2462023-24
- 2752024-25
Operator accounts
From each operator's standalone audited accounts, in ₹ crore. Income can include outside project work and grants.
Kochi Metro Rail Limited
Joint venture of the Union and Kerala governments. Income includes ₹82 crore of non-cash grant income on interest-free loans.
| Year | Income | Fares | Before interest and depreciation | Net result | Debt |
|---|---|---|---|---|---|
| 2024-25 | 275 | 112 | 102 | −431 | 4,868 |
| 2023-24 | 246 | – | 41 | −435 | 4,642 |
| 2022-23 | 201 | 75 | – | −336 | – |
| 2020-21 | – | – | – | −334 | – |
| 2019-20 | – | – | – | −310 | – |
| 2018-19 | – | – | – | −281 | – |
| 2017-18 | – | – | – | −167 | – |
Central money released
Equity, pass-through loans and grants from the Housing and Urban Affairs ministry, in ₹ crore, from a Lok Sabha answer of April 2026.
- 02020-21
- 02021-22
- 1472022-23
- 02023-24
- 02024-25
- 662025-26*, to 2026-03-30
* to 2026-03-30
Sources14
- Lok Sabha unstarred question 1054, Status of Metro Projects, answered 2026-02-05sansad.inPDF document
- KMRL: Phase II statuskochimetro.orgPublisher page
- Lok Sabha starred question 270, Length of Metro Rail Network, answered 2023-12-21sansad.inPDF document
- Lok Sabha unstarred question 4460, Metro Rail Network, answered 2025-03-27sansad.inPDF document
- Lok Sabha unstarred question 3110, Metro Rail Network and its Achievements, answered 2025-12-18sansad.inPDF document
- Lok Sabha unstarred question 6274, Metro Rail Projects, answered 2026-04-02sansad.inPDF document