Surat Metro

Surat. Run by Gujarat Metro Rail Corp. (GMRC).

Running
0 km
Being built
40.4 km
First opened
Not yet open
Being built 40.4 km

Next: Dream City to Althan stretch, reported target, Nov 2026. Targets often slip.

Phase 1 remains under construction at 81.10% physical progress in June 2026. Trial runs began in March 2026 on the 8.5 km Dream City-Althan Tenement stretch; DeshGujarat reported a target of end-November 2026, and no safety clearance has been found.

Route km in the ministry's tables

None of the ministry's city tables in Lok Sabha answers shows Surat with track running. Its table of February 2026 gives 40.4 km under construction.

Being built

Physical progress at 30 Jun 2026 and sanctioned cost, from a Lok Sabha answer.

  1. Surat Metro Rail Project81.1%

    40.4 km, ₹12,020 cr

Operator accounts

From each operator's standalone audited accounts, in ₹ crore. Income can include outside project work and grants.

Gujarat Metro Rail Corporation (GMRC) Limited

50:50 special purpose vehicle. Income fell from ₹873 crore because 2023-24 carried a ₹573 crore foreign exchange gain on loans. In 2024-25 grants of ₹217 crore and deposit interest of ₹118 crore outweigh passenger revenue of ₹48 crore.

YearIncomeFaresBefore interest and depreciationNet resultDebt
2024-253864873−5508,535
2023-24873356272406,428
2022-23149––––

Central money released

Equity, pass-through loans and grants from the Housing and Urban Affairs ministry, in ₹ crore, from a Lok Sabha answer of April 2026.

  1. 02020-21
  2. 6392021-22
  3. 1,6982022-23
  4. 2,2642023-24
  5. 2,2642024-25
  6. 3652025-26*, to 2026-03-30

* to 2026-03-30