India is building 8.0 GW of nuclear power, almost as much as it built in 57 years
10 reactors are under construction, on top of 24 installed units with 8,780 MW. Nuclear is 1.6% of India's power capacity and made 3.0% of its electricity in 2025-26.
Nuclear electricity made
55.2 TWh36.1 TWh
Share of India's electricity
3.0%3.3%
Being built
Together these add 8,000 MW. Another 2,800 MW is planned, and it is listed last.
- PFBR Kalpakkam (BHAVINI)Kalpakkam, Tamil Nadu500 MW470 MW netUnder construction, FBRSodium-cooled fast breeder reactor, Stage II of India's three-stage programme. First criticality on 6 April 2026; no grid connection announced as of 6 November 2026.First critical 6 Apr 2026
- Rajasthan-8 (RAPS-8)Rawatbhata, Rajasthan700 MW630 MW netUnder construction, PHWRInitial fuel loading began on 19 September 2026 with AERB permission; first approach to criticality is next. NPCIL expects commercial operation in the current financial year.
- Kudankulam-3 (KKNPP-3)Kudankulam, Tamil Nadu1,000 MW917 MW netUnder construction, VVERConstruction start 29 June 2017; fuel delivered December 2025; Spillage to Open Reactor, a commissioning milestone, reached on 25 April 2026.
- Kudankulam-4 (KKNPP-4)Kudankulam, Tamil Nadu1,000 MW917 MW netUnder construction, VVERConstruction start 23 October 2017; commissioning expected after KKNPP-3.
- Kudankulam-5 (KKNPP-5)Kudankulam, Tamil Nadu1,000 MW917 MW netUnder construction, VVERFirst concrete poured 29 June 2021; reactor pressure vessel erected in June 2026.
- Kudankulam-6 (KKNPP-6)Kudankulam, Tamil Nadu1,000 MW917 MW netUnder construction, VVERFirst concrete poured December 2021; current operator target September 2027.
- GHAVP-1 (Gorakhpur-1)Gorakhpur, Fatehabad, Haryana700 MW630 MW netUnder construction, PHWRFirst-pour-of-concrete in 2022; first PHWR built outside the legacy nuclear states.
- GHAVP-2 (Gorakhpur-2)Gorakhpur, Fatehabad, Haryana700 MW630 MW netUnder construction, PHWRTwin unit of GHAVP-1, currently under construction; commissioning targets not yet published.
- Kaiga-5 (KGS-5)Kaiga, Karnataka700 MW630 MW netUnder construction, PHWRFirst-pour-of-concrete ceremony held 1 March 2026; part of the 10-reactor fleet-mode 700 MW PHWR programme.
- Kaiga-6 (KGS-6)Kaiga, Karnataka700 MW630 MW netUnder construction, PHWRTwin unit of KGS-5; concrete pour March 2026.
- Mahi Banswara 1-4Banswara, Rajasthan2,800 MW2,520 MW netPlanned, PHWRFoundation stone laid by the Prime Minister on 25 September 2025 for four IPHWR-700 units (4 × 700 MW); commissioning targets 2031-2034.
Running now
NPCIL's plants have generated 1,017 TWh since October 1969, counted through Oct 2026. In 2026-27 to Oct 2026 the fleet ran at a 90% capacity factor. The 23 running reactors at 7 sites total 8,560 MW gross and 7,730 MW net.
Every NPCIL unit, from commercial operation to Oct 2026
- Boiling water (BWR)
- Pressurised heavy water (PHWR)
- Pressurised water (VVER)
- Licence valid to
Capacity factor by unit, 2026-27 to date
- KGS-4107%1,213 MU
- KGS-3107%1,209 MU
- RAPS-6104%1,180 MU
- RAPS-5104%1,171 MU
- KAPS-2100%1,129 MU
- KKNPS-298%5,027 MU
- NAPS-197%1,091 MU
- KAPS-494%3,369 MU
- KKNPS-193%4,767 MU
- MAPS-293%1,050 MU
- KAPS-392%3,295 MU
- KGS-291%1,027 MU
- TAPS-290%509 MU
- RAPS-788%3,168 MU
- RAPS-488%997 MU
- RAPS-285%875 MU
- TAPS-381%2,253 MU
- RAPS-381%916 MU
- NAPS-280%908 MU
- KAPS-179%891 MU
- TAPS-463%1,746 MU
- TAPS-162%507 MU
- KGS-10%0 MU
- MAPS-10%0 MU
Plants
- KudankulamKudankulam Nuclear Power Station, 2 units2,000 MW9,794 MU this year
- KakraparKakrapar Atomic Power Station, 4 units1,840 MW8,684 MU this year
- RawatbhataRajasthan Atomic Power Station, 7 units1,780 MW8,307 MU this year
- TarapurTarapur Atomic Power Station, 4 units1,400 MW5,015 MU this year
- KaigaKaiga Generating Station, 4 units880 MW3,449 MU this year
- NaroraNarora Atomic Power Station, 2 units440 MW1,999 MU this year
- KalpakkamMadras Atomic Power Station, 2 units440 MW1,050 MU this year
Operating reactors
| Kudankulam-1 (KKNPP-1)Kudankulam, Tamil Nadu. NPCIL | VVER | 1,000 MW | 932 MW | 13 Jul 2013 | 31 Dec 2014 |
|---|---|---|---|---|---|
| Kudankulam-2 (KKNPP-2)Kudankulam, Tamil Nadu. NPCIL | VVER | 1,000 MW | 932 MW | 10 Jul 2016 | 31 Mar 2017 |
| Kakrapar-3Kakrapar, Gujarat. NPCIL | PHWR | 700 MW | 630 MW | 22 Jul 2020 | 30 Jun 2023 |
| Kakrapar-4Kakrapar, Gujarat. NPCIL | PHWR | 700 MW | 630 MW | 17 Dec 2023 | 31 Mar 2024 |
| Rajasthan-7 (RAPS-7)Rawatbhata, Rajasthan. NPCIL | PHWR | 700 MW | 630 MW | 19 Sept 2024 | 15 Apr 2025 |
| Tarapur-3 (TAPS-3)Tarapur, Maharashtra. NPCIL | PHWR | 540 MW | 482 MW | 21 May 2006 | 18 Aug 2006 |
| Tarapur-4 (TAPS-4)Tarapur, Maharashtra. NPCIL | PHWR | 540 MW | 378 MW | 6 Mar 2005 | 12 Sept 2005 |
| Kakrapar-1Kakrapar, Gujarat. NPCIL | PHWR | 220 MW | 202 MW | 3 Sept 1992 | 6 May 1993 |
| Kakrapar-2Kakrapar, Gujarat. NPCIL | PHWR | 220 MW | 202 MW | 8 Jan 1995 | 1 Sept 1995 |
| Madras-2 (MAPS-2)Kalpakkam, Tamil Nadu. NPCIL | PHWR | 220 MW | 205 MW | 12 Aug 1985 | 21 Mar 1986 |
| Narora-1 (NAPS-1)Narora, Uttar Pradesh. NPCIL | PHWR | 220 MW | 202 MW | 12 Mar 1989 | 1 Jan 1991 |
| Narora-2 (NAPS-2)Narora, Uttar Pradesh. NPCIL | PHWR | 220 MW | 202 MW | 24 Oct 1991 | 1 Jul 1992 |
| Rajasthan-3 (RAPS-3)Rawatbhata, Rajasthan. NPCIL | PHWR | 220 MW | 202 MW | 24 Dec 1999 | 1 Jun 2000 |
| Rajasthan-4 (RAPS-4)Rawatbhata, Rajasthan. NPCIL | PHWR | 220 MW | 202 MW | 3 Nov 2000 | 23 Dec 2000 |
| Rajasthan-5 (RAPS-5)Rawatbhata, Rajasthan. NPCIL | PHWR | 220 MW | 202 MW | 24 Nov 2009 | 4 Feb 2010 |
| Rajasthan-6 (RAPS-6)Rawatbhata, Rajasthan. NPCIL | PHWR | 220 MW | 202 MW | 28 Jan 2010 | 31 Mar 2010 |
| Kaiga-1 (KGS-1)Kaiga, Karnataka. NPCIL | PHWR | 220 MW | 202 MW | 26 Sept 2000 | 16 Nov 2000 |
| Kaiga-2 (KGS-2)Kaiga, Karnataka. NPCIL | PHWR | 220 MW | 202 MW | 24 Sept 1999 | 16 Mar 2000 |
| Kaiga-3 (KGS-3)Kaiga, Karnataka. NPCIL | PHWR | 220 MW | 202 MW | 26 Feb 2007 | 6 May 2007 |
| Kaiga-4 (KGS-4)Kaiga, Karnataka. NPCIL | PHWR | 220 MW | 202 MW | 27 Nov 2010 | 20 Jan 2011 |
| Rajasthan-2 (RAPS-2)Rawatbhata, Rajasthan. NPCIL | PHWR | 200 MW | 187 MW | 8 Oct 1980 | 1 Apr 1981 |
| Tarapur-1 (TAPS-1)Tarapur, Maharashtra. NPCIL | BWR | 160 MW | 150 MW | – | 28 Oct 1969 |
| Tarapur-2 (TAPS-2)Tarapur, Maharashtra. NPCIL | BWR | 160 MW | 150 MW | – | 28 Oct 1969 |
Capacity built up over time
8,560 MW320 MW
Reactors added each decade
- 1960s2 reactors
- 1980s2 reactors
- 1990s4 reactors
- 2000s7 reactors
- 2010s5 reactors
- 2020s3 reactors
Capacity by site
- KudankulamTamil Nadu, 2 units2,000 MW
- KakraparGujarat, 4 units1,840 MW
- RawatbhataRajasthan, 6 units1,780 MW
- TarapurMaharashtra, 4 units1,400 MW
- KaigaKarnataka, 4 units880 MW
- NaroraUttar Pradesh, 2 units440 MW
- KalpakkamTamil Nadu, 1 unit220 MW
Capacity by reactor type
- PHWRPressurised heavy water19 reactors, 6,240 MW
- VVERRussian pressurised water2 reactors, 2,000 MW
- BWRBoiling water2 reactors, 320 MW
Law and fuel
- SHANTI Act2025Received assent in December 2025 and replaces the Atomic Energy Act 1962 and the Civil Liability for Nuclear Damage Act 2010. Private companies can apply for licences for civil nuclear activities, operator liability moves to a tiered structure, and foreign direct investment is not provided for. Draft rules were published for comment on 14 August 2026; final rules had not been notified as of 6 November 2026.
- AERB: Atomic Energy Regulatory Board1983Constituted under the Atomic Energy Act 1962. Issues siting consents, construction authorisations, fuel-loading approvals, and operating licences for every NPCIL/BHAVINI unit. Reports to the Atomic Energy Commission.
- Civil Liability for Nuclear Damage Act2010Repealed by the SHANTI Act. It capped the operator's liability at ₹1,500 crore per nuclear incident with a statutory right of recourse against suppliers, the contested clause that slowed foreign reactor sales, and created the Nuclear Damage Claims Commission.
- India-US Civil Nuclear Agreement (123 Agreement) + NSG waiver2008Bilateral 123 Agreement signed October 2008; the Nuclear Suppliers Group granted India a clean waiver in September 2008. Together they ended India's three-decade civil nuclear isolation post-1974, reopened uranium imports, and unlocked the Kudankulam expansion and the planned Westinghouse and EDF projects.
- IAEA Safeguards + Additional Protocol2014Civil-military separation plan (2006) placed designated reactors under IAEA safeguards. The India-specific Safeguards Agreement entered into force in 2009 and the Additional Protocol entered into force on 25 July 2014, extending IAEA inspection access to declared civil facilities.
- Three-stage nuclear programmeongoingDAE's long-term roadmap formulated by Homi Bhabha. Stage I: natural-uranium PHWRs (the operating fleet). Stage II: plutonium-fuelled fast breeder reactors using Stage I plutonium (PFBR Kalpakkam achieved first criticality on 6 April 2026, kicking off Stage II). Stage III: thorium-fuelled advanced heavy-water reactor (AHWR-300) using India's vast thorium reserves at Kerala's monazite sands.
- Bharat Small Reactors (BSR) initiative2024-25Announced in the Union Budget 2024-25 with a ₹20,000 crore Nuclear Energy Mission outlay (Budget 2025-26). NPCIL is building a 220 MWe PHWR-class fleet for industrial captive use, and DAE has tendered for indigenous SMR design partners, together targeting 100 GW of nuclear capacity by 2047.
- UCIL: Uranium Corporation of India LtdUranium mining and millingDAE PSU, established 1967. Operates India's only uranium mines. The Jharkhand Singhbhum belt has been the historical mainstay; Tummalapalle in Andhra Pradesh hosts one of the world's largest single uranium deposits and is the country's first alkaline-leach mill.Jaduguda (Jharkhand), Turamdih (Jharkhand), Bagjata (Jharkhand), Tummalapalle (Andhra Pradesh)
- NFC: Nuclear Fuel Complex, HyderabadFuel fabrication and zirconium componentsManufactures the natural-uranium fuel bundles used in PHWRs and the enriched UO2 fuel imported for the VVER-1000 reactors at Kudankulam, plus all zirconium-alloy structural components for the Indian fleet.Hyderabad (Telangana), Kota (Rajasthan, NFC-Kota)
- Heavy Water Board (HWB)Heavy water (D2O) productionOperates India's heavy-water plants, the moderator and primary coolant for the PHWR fleet. India is one of the few countries with full D2O self-sufficiency and is now an exporter.HWP Kota (Rajasthan), HWP Manuguru (Telangana), HWP Talcher (Odisha), HWP Tuticorin (Tamil Nadu), HWP Hazira (Gujarat), HWP Thal (Maharashtra), HWP Baroda (Gujarat)
This page covers the civil programme only. Strategic facilities (CIRUS, Dhruva, the FBTR research reactor, military reprocessing), reactor-grade plutonium stocks and the research reactors at BARC Trombay are left out.
Sources27
- NPCIL: All Plantsnpcil.nic.inPublisher page
- NPCIL: Operating Performance, Tarapurnpcil.nic.inPublisher page
- NPCIL: Operating Performance, Rawatbhatanpcil.nic.inPublisher page
- NPCIL: Operating Performance, Kudankulamnpcil.nic.inPublisher page
- NPCIL: Operating Performance, Kakraparnpcil.nic.inPublisher page
- NPCIL: Operating Performance, Naroranpcil.nic.inPublisher page
NPCIL: Operating Performance, KaigaNPCIL: Operating Performance, KalpakkamAERB: Validity of the operating licence of various NPPs (March 2026)IAEA PRIS: India country pageDAE / PIB: Nuclear projects under implementation, 29 January 2026NPCIL: RAPP-8 initial fuel loading began on 19 September 2026NPCIL: KKNPP-3 Spillage to Open Reactor on 25 April 2026NPCIL: KKNPP-5 reactor pressure vessel erected in June 2026AERB: Atomic Energy Regulatory BoardDAE / PIB: PFBR attained first criticality on 6 April 2026World Nuclear News: India's SHANTI Bill completes legislative processDAE: Draft SHANTI Rules, 14 August 2026UCIL: Uranium Corporation of India LtdNFC: Nuclear Fuel Complex, HyderabadHeavy Water Board (DAE)Department of Atomic Energy (DAE)CEA: Executive Summary on Power Sector, September 2026Civil Liability for Nuclear Damage Act, 2010 (PRS Legislative)Wikipedia: India-United States Civil Nuclear AgreementIAEA: India safeguards and Additional ProtocolUnion Budget 2025-26: Nuclear Energy Mission (PIB)