Rajasthan Atomic Power Station
Rawatbhata, Kota, Rajasthan
- Units
- 7
- 1,780 MW rated
- In service since
- 1973
- RAPS Unit-1, 16 Dec 1973
- Generated since then
- 208 TWh
- NPCIL, to Oct 2026
- Generated in 2026-27
- 8,307 MU
- April to Oct 2026
Units, from commercial operation
- Pressurised heavy water (PHWR)
- Licence valid to
1970198019902000201020202030
Capacity factorRAPS-1ShutRAPS-285%RAPS-381%RAPS-488%RAPS-5104%RAPS-6104%RAPS-788%Every unit
- UnitTypeCapacityIn serviceLifetime outputLicence
- RAPS-1PHWRShut down16 Dec 197312,089 MUValid to Aug 2029
- RAPS-2PHWR200 MW1 Apr 198150,779 MUValid to Aug 2029
- RAPS-3PHWR220 MW1 Jun 200039,287 MUValid to Oct 2027
- RAPS-4PHWR220 MW23 Dec 200041,778 MUValid to Oct 2027
- RAPS-5PHWR220 MW4 Feb 201030,527 MUValid to Mar 2030
- RAPS-6PHWR220 MW31 Mar 201028,016 MUValid to Mar 2030
- RAPS-7PHWR700 MW15 Apr 20255,370 MUNot in AERB's list
RAPS Unit -1 is under long shutdown since October 9, 2004.
Capacity factor, 2026-27 to date
- RAPS-6104%1,180 MU
- RAPS-5104%1,171 MU
- RAPS-788%3,168 MU
- RAPS-488%997 MU
- RAPS-285%875 MU
- RAPS-381%916 MU
Being built here
- Rajasthan-8 (RAPS-8)NPCIL (Nuclear Power Corporation of India Ltd)700 MWUnder construction, PHWRInitial fuel loading began on 19 September 2026 with AERB permission; first approach to criticality is next. NPCIL expects commercial operation in the current financial year.
Sources6
- NPCIL: All Plantsnpcil.nic.inPublisher page
- NPCIL: Operating Performance, Rawatbhata, Kota, Rajasthannpcil.nic.inPublisher page
- AERB: Validity of the operating licence of various NPPs (March 2026)aerb.gov.inPDF document
- IAEA PRIS: India country pagepris-stats.iaea.orgPublisher page
- NPCIL: RAPP-8 initial fuel loading began on 19 September 2026npcil.nic.inPDF document
- DAE / PIB: Nuclear projects under implementation, 29 January 2026pib.gov.inPublisher page